Part 4 of 13 · Redevelopment Guide for Housing Societies (Pune & PCMC)

By Advocate Ketan Palshikar | Last updated: 14 November 2026 | Based on Government Order No. SGHYO-2026/CR-108/14-S dated 30 September 2026


Introduction: The First Formal Decision in the Redevelopment Process

The decision to redevelop a cooperative housing society’s building is not an ordinary administrative decision of the Managing Committee. It is a significant decision affecting the property, contractual rights, financial interests and future accommodation of every member.

The Maharashtra Government Order dated 30 September 2026 prescribes a structured procedure for initiating redevelopment through a Special General Body Meeting (SGM).

The meeting is intended to consider the preliminary decision on redevelopment, provide members an opportunity to express their views, select an Architect / Project Management Consultant (PMC), determine the scope of professional work and establish the initial roadmap for the project.

The procedure includes specific requirements concerning:

  • Requisition by members.
  • Convening of the SGM.
  • Notice and proof of service.
  • Selection of Architect / PMC.
  • Written suggestions from members.
  • Quorum.
  • Approval by at least 51% of total membership.
  • Eligible virtual participation.
  • Physical attendance.
  • Recording of members’ views.
  • Written consent from members voting in favour.
  • Appointment of the selected Architect / PMC.

A society must also read these provisions with Section 76 of the Maharashtra Co-operative Societies Act, 1960 and the applicable Maharashtra Co-operative Societies Rules, 1961.

This article explains the procedure step by step.

1. Who Can Initiate the Redevelopment SGM?

Under Paragraph 4 of the 2026 Government Order, at least one-fifth of the society’s members may submit a written application to the Secretary of the duly elected and legally constituted Managing Committee seeking an SGM to consider redevelopment.

The requisition should contain the members’ proposed plans, suggestions and recommendations concerning redevelopment.

1.1 What Is the Required Number of Members?

The 2026 Government Order refers to at least one-fifth of the members.

For example:

Total MembershipOne-Fifth of Members
204
306
408
5010
7515
10020
15030
20040

The society should calculate the threshold with reference to the legally relevant membership position and verify the applicable statutory and bye-law provisions.

Section 76(1)(i) of the Maharashtra Co-operative Societies Act, 1960 provides for a written requisition by one-fifth of the members or the number specified in the bye-laws for this purpose, whichever is lower.

Accordingly, the society should examine Section 76 and its registered bye-laws rather than applying the Government Order in isolation.

1.2 Who Should Receive the Requisition?

The requisition should be addressed to the Secretary of the Managing Committee.

It should be:

  • In writing.
  • Signed by the requisite number of members.
  • Clear about the purpose of the meeting.
  • Accompanied by the members’ redevelopment proposals or suggestions.
  • Delivered in a manner that creates reliable proof of receipt.

The society should acknowledge receipt and preserve the original requisition.

1.3 Recommended Contents of the Requisition

The requisition may identify:

  1. Name and registration number of the society.
  2. Address of the society.
  3. Names and membership details of requisitioning members.
  4. Relevant flat / shop numbers.
  5. Statement that the requisition is made under Section 76 of the MCS Act and the applicable redevelopment Government Order.
  6. Request to convene an SGM to consider the preliminary redevelopment proposal.
  7. Brief suggestions or recommendations concerning redevelopment.
  8. Signatures and date.

The requisition should not be confused with a final redevelopment resolution. It merely seeks a meeting at which the matter will be considered.


2. The Important Legal Issue: One Month Under Section 76 vs Two Months Under the 2026 GR

This is a particularly important issue for Managing Committees.

2.1 What Does Section 76 Say?

Section 76(1) of the Maharashtra Co-operative Societies Act, 1960 provides that a Special General Body Meeting shall be called within one month upon receipt of a valid written requisition from the prescribed number of members.

The provision also gives the Registrar power to intervene if the meeting is not called in accordance with the statutory requisition.

Section 76(2) further provides for possible action against the responsible officer or committee member for failure, without reasonable excuse, to call the meeting.

2.2 What Does the 2026 Government Order Say?

Paragraph 4 of the 2026 Government Order states that:

  • The Managing Committee should take note of the requisition within 8 days.
  • The Secretary should convene the SGM within 2 months.
  • The meeting notice should be issued at least 14 days in advance.

2.3 How Should the Two Provisions Be Read Together?

There is an apparent difference between the one-month period under Section 76 and the two-month period stated in Paragraph 4 of the Government Order.

The Government Order is issued under Section 79A of the MCS Act. It should be read consistently with the parent statute and cannot simply be assumed to override an inconsistent statutory requirement.

A Bombay High Court decision dated 8 September 2026 in Ratanji S. Desai v. State of Maharashtra considered the statutory requirement under Section 76 and referred to the one-month period for convening an SGM upon a valid requisition.

Practical Recommendation

A Managing Committee should not rely on the two-month period in the Government Order as an automatic extension of the statutory period under Section 76.

Where a valid requisition is received, the safer course is to proceed in a manner that complies with the one-month statutory requirement, while also meeting the other procedural requirements of the 2026 Government Order.

The society should obtain project-specific legal advice if any issue arises concerning the validity of the requisition, membership count, applicable bye-laws or calculation of the statutory period.


3. What Happens After the Requisition Is Received?

Paragraph 4 of the 2026 Government Order specifies that the Managing Committee should take note of the requisition in its meeting within 8 days of receipt.

The society should therefore maintain a clear record of:

  • Date of receipt.
  • Date on which the requisition was placed before the Managing Committee.
  • Relevant committee resolution.
  • Date fixed for the SGM.
  • Steps taken to obtain professional quotations.
  • Notice issued to members.

The Managing Committee should not ignore a valid requisition or indefinitely postpone the matter.

3.1 Can the Managing Committee Reject the Requisition?

The Managing Committee should examine whether the requisition satisfies the statutory and bye-law requirements.

If the requisition is defective—for example, because it does not contain the required number of valid signatures—the society should record the specific defect and communicate it appropriately.

It should not reject a valid requisition merely because some committee members oppose redevelopment or prefer not to discuss the proposal.

The statutory power of members to requisition an SGM must be respected.

3.2 What If the Managing Committee Does Not Convene the Meeting?

Section 76(3) of the MCS Act empowers the Registrar or a person authorised by the Registrar to call the meeting if the society fails to convene it in accordance with the statutory requisition.

Such a meeting is deemed to be a meeting duly called by the committee.

The consequences under Section 76(2) may also arise against responsible persons, subject to the statutory procedure and opportunity of hearing.

A Managing Committee should therefore treat a valid requisition as a statutory obligation, not merely a request that it may accept or reject at its discretion.


4. Obtaining Quotations from Architects / PMC Before the SGM

An important feature of the 2026 procedure is that the Managing Committee must obtain professional quotations before the initial redevelopment SGM.

Paragraph 4 requires the committee to obtain quotations from at least three architects registered with the Council of Architecture under the Architects Act, 1972, or eligible Project Management Consultants (PMC) from the relevant Government / local authority panel, as specified in the Government Order.

The purpose is to enable members to select an appropriate professional for preparing the redevelopment project report.

4.1 Why Must Quotations Be Obtained Before the SGM?

The members should not be asked to select an Architect / PMC without knowing:

  • Who the proposed professionals are.
  • Their qualifications.
  • Their experience.
  • Their proposed scope of work.
  • Their professional fees.
  • Their proposed deliverables.
  • Their expected timeline.

The quotations provide a basis for an informed selection.

4.2 What Should the Quotations Contain?

The society should request each professional to provide:

  1. Name and professional details.
  2. Registration and panel details, as applicable.
  3. Experience in cooperative housing society redevelopment.
  4. Details of similar completed projects.
  5. Proposed scope of work.
  6. Project-report deliverables.
  7. Professional fees and payment milestones.
  8. Expected time for preparation of the report.
  9. Whether the professional will assist during tendering and developer selection.
  10. Whether the professional will provide construction-stage PMC services, if separately agreed.
  11. Disclosure of any relevant conflict of interest.

The society should avoid comparing quotations only on the amount of professional fees.

4.3 Does the PMC Have to Be Selected at the Initial SGM?

Yes. Under Paragraph 4, the quotations are obtained before the SGM and one professional is selected at that meeting.

The members should also determine the scope of work and the relevant terms and conditions for the professional’s engagement.

The appointment should subsequently be documented in writing.


5. Notice of the Special General Body Meeting

The 2026 Government Order requires the meeting agenda to be given to every member at least 14 days before the meeting.

The society should maintain proof of service.

5.1 What Should the Notice Contain?

The notice should clearly state:

  • Name and address of the society.
  • Date of issue.
  • Date of the SGM.
  • Time of the meeting.
  • Venue.
  • Detailed agenda.
  • Purpose of the meeting.
  • Information about the proposed redevelopment discussion.
  • Details of the Architect / PMC quotations.
  • Documents available for inspection.
  • Procedure for submitting written suggestions.
  • Applicable attendance and participation arrangements.

The notice should not contain vague agenda items such as “discussion about building matters” where the actual purpose is to consider redevelopment.

5.2 Suggested Agenda for the Initial Redevelopment SGM

The agenda may include the following items, in the sequence appropriate to the meeting:

  1. To consider the proposal for redevelopment of the society’s building.
  2. To consider the preliminary redevelopment options and members’ suggestions.
  3. To consider the preliminary decision whether the society should proceed with redevelopment.
  4. To consider the quotations received from at least three eligible Architects / PMCs.
  5. To select one Architect / PMC for preparation of the redevelopment project report.
  6. To decide the scope of work and professional terms and conditions.
  7. To authorise the Secretary / Managing Committee to issue the appointment letter and execute the professional engagement agreement in accordance with the approved terms.
  8. To consider any other matter permitted under the applicable law and meeting procedure.

The final agenda must accurately reflect the business proposed to be transacted.

5.3 Proof of Service

The society should preserve:

  • Hand-delivery acknowledgements.
  • Postal receipts and tracking records.
  • Email transmission records.
  • Other permitted electronic delivery records.
  • Copies of the notice and agenda.
  • Notice-board display records, where applicable.

A society should not assume that placing a notice on the notice board alone is sufficient when the Government Order requires the agenda to be given to every member.


6. Members’ Right to Submit Written Suggestions Before the SGM

Paragraph 5 of the 2026 Government Order gives members an opportunity to submit realistic redevelopment plans, suggestions and recommendations in writing.

These must be submitted to the Managing Committee at least 8 days before the meeting.

6.1 What Can Members Suggest?

Members may submit suggestions concerning:

  • Additional carpet area.
  • Corpus.
  • Transit rent.
  • Security deposit.
  • Shifting charges.
  • Parking.
  • Amenities.
  • Construction quality.
  • Flat configuration.
  • Accessibility.
  • Senior-citizen requirements.
  • Commercial premises.
  • Open spaces and gardens.
  • Building specifications.
  • Project timelines.
  • Developer selection criteria.
  • Other matters affecting their rehabilitation and the society’s redevelopment.

At the initial SGM stage, these suggestions should be treated as inputs for the redevelopment process, not as final contractual commitments.

6.2 How Should the Society Handle Written Suggestions?

The Managing Committee should:

  1. Receive and acknowledge the suggestions.
  2. Maintain a register of submissions.
  3. Record the name of the submitting member.
  4. Place the suggestions before the meeting.
  5. Ensure that relevant views are considered.
  6. Preserve the submissions with the meeting records.

The society should not discard suggestions merely because they differ from the Managing Committee’s preferred proposal.


7. Quorum for the Initial Redevelopment SGM

Paragraph 6 of the 2026 Government Order prescribes quorum of two-thirds of the society’s total membership.

This is a special quorum requirement for redevelopment-related meetings under the Government Order.

7.1 Example: Society Having 100 Members

If a society has 100 members:

[
\text{Quorum} = \frac{2}{3}\times100 = 66.67
]

The number must be rounded up.

Therefore, the required quorum is 67 members.

The society should calculate quorum with reference to its legally relevant total membership.

7.2 What If Quorum Is Not Present?

If the required quorum is not present:

  1. The meeting must be adjourned.
  2. The adjourned meeting must be convened within the next one month.
  3. At least 7 days’ notice must be given for the adjourned meeting.
  4. If quorum is again not present, the meeting must be cancelled.
  5. The redevelopment proposal cannot be brought again before the SGM for approval for the next 3 months, as specified in the Government Order.

The society should carefully document the original meeting, adjournment, notice for the adjourned meeting and the attendance at the second meeting.

7.3 Can the Society Reduce the Quorum Because Members Are Not Interested?

No. The society cannot simply reduce the prescribed quorum to proceed with the redevelopment proposal.

The prescribed procedure must be followed.


8. Virtual Participation in the Initial SGM

The 2026 Government Order introduces an express facility for eligible members to participate through a remote system / Video Conferencing.

The provision recognises members who cannot attend physically because they are:

  • Residing abroad.
  • Seriously ill.
  • Persons with disabilities.
  • Unable to attend for other unavoidable reasons.

Such eligible virtual attendance is counted for the purpose of quorum and the 51% approval requirement.

However, the Government Order imposes an additional condition.

At least 51% of the society’s total membership must be physically present at the meeting.

8.1 Example: Society Having 100 Members

Consider a society having 100 members.

The requirements are:

ParticularsRequirement
Total membership100
Two-thirds quorum67
Minimum physical attendance51
Minimum approval51

A possible attendance composition could be:

  • 51 members physically present.
  • 16 eligible members attending through VC.
  • Total participation: 67 members.

The quorum requirement is satisfied, subject to the prescribed conditions.

8.2 Can Any Member Attend Through VC?

The Government Order identifies specified circumstances for virtual participation.

It should not be treated as an unrestricted option for every member to attend virtually merely for convenience.

The society should establish a procedure to verify eligibility and participation.

8.3 What Should the Society Arrange?

The society should consider:

  • Reliable video-conferencing facilities.
  • Identity verification.
  • Attendance records.
  • Confirmation that the participant can hear and participate.
  • A mechanism for recording votes.
  • Prevention of duplicate participation.
  • Recording of the meeting.
  • Preservation of the electronic attendance and voting records.

The society should document the arrangements in advance.


9. The 51% Approval Requirement: How Is the Initial Redevelopment Decision Passed?

The initial decision whether to proceed with redevelopment requires approval of at least 51% of the society’s total membership.

This requirement is distinct from the two-thirds quorum.

9.1 Example: Society Having 100 Members

The society has 100 members.

  • Required quorum: 67.
  • Minimum affirmative approval: 51.
  • Members present may be a combination of physical and eligible virtual participants.
  • At least 51 members must be physically present.

If 67 members participate, at least 51 must support the proposal.

If 75 members participate, at least 51 must still support the proposal.

The threshold is not merely 51% of the members present.

9.2 Important Distinction: Quorum, Physical Attendance and Approval

These are three separate requirements:

Quorum: At least two-thirds of total membership must participate, counting eligible virtual attendance.

Physical attendance: At least 51% of total membership must be physically present.

Approval: At least 51% of total membership must support the redevelopment decision, counting eligible virtual votes as permitted.

A society should record each figure separately.

9.3 Can Absent Members’ Written Consent Be Counted?

Paragraph 6 of the 2026 Government Order states that the views, opinions or consent of members who are absent from the meeting are not to be considered in the meeting’s decision-making process merely because they are communicated in writing, orally or otherwise.

The approval must be established through the prescribed meeting procedure.

A member who does not attend cannot simply send a letter stating that they support the resolution and expect that letter to be counted as a vote at the meeting.


10. What Business Should Be Transacted at the Initial SGM?

Once the preliminary redevelopment decision is considered and approved in accordance with the prescribed voting requirement, the meeting should proceed with the remaining agenda items.

The 2026 Government Order contemplates the following business:

  1. Selection of an experienced Architect / PMC from the eligible quotations.
  2. Determination of the scope of work and terms and conditions of the professional appointment.
  3. Presentation of the proposed redevelopment programme / roadmap.
  4. Consideration of members’ suggestions, recommendations and objections.
  5. Recording of members’ views in the minutes with their names.

10.1 Should the SGM Approve the Final Development Scheme?

No.

The initial SGM is not the stage at which the society finally approves the developer, Development Agreement or complete building plan.

The purpose at this stage is to take the preliminary decision to proceed with redevelopment and appoint the professional who will prepare the project report.

The project report, tender process and developer selection will follow through the subsequent stages prescribed in the Government Order.

10.2 Should the SGM Decide the Exact Additional Carpet Area?

The initial meeting may discuss members’ expectations and suggestions, but the actual rehabilitation and development proposal must be assessed through the project report and applicable planning regulations.

The society should avoid making unconditional promises regarding additional carpet area before the technical and financial feasibility is established.


11. Recording Members’ Opinions and Objections in the Minutes

The 2026 Government Order specifically requires members’ views, suggestions and objections to be recorded in the meeting minutes with their names.

This is an important transparency requirement.

11.1 What Should Be Recorded?

The minutes should include:

  • Names of members who spoke.
  • Suggestions made.
  • Objections raised.
  • Clarifications given.
  • Important questions and responses.
  • Decisions taken.
  • Voting result.
  • Names or records of members voting in favour, against or otherwise, as required for the relevant resolution.
  • Details of the selected Architect / PMC.
  • Approved scope and terms of professional engagement.

The minutes should not merely state that “the matter was discussed in detail and approved.”

11.2 Can the Society Ignore Dissenting Opinions?

No.

The Government Order requires members’ views and suggestions to be considered and recorded.

However, the fact that a member has expressed an objection does not automatically mean that the proposal cannot proceed if the statutory and prescribed approval requirements are satisfied.

The society should distinguish between:

  • The right to express an opinion.
  • The right to have the opinion recorded.
  • The voting entitlement.
  • The legal effect of the resolution passed by the required majority.

11.3 Why Is Proper Recording Important?

Accurate minutes can help establish:

  • Whether the agenda was followed.
  • Whether members were given an opportunity to speak.
  • Whether relevant objections were considered.
  • Whether the prescribed quorum existed.
  • Whether the required majority was obtained.
  • Whether the professional was selected in accordance with the procedure.

The minutes should be prepared contemporaneously and preserved with supporting records.


12. Written Consent from Members Who Voted in Favour

Paragraph 7 of the 2026 Government Order requires the Managing Committee to obtain written consent from members who voted in favour of the initial redevelopment resolution before taking further steps in the redevelopment process.

This is a separate requirement from the vote recorded during the SGM.

12.1 Voting and Written Consent Are Different

The society should maintain separate records of:

  1. Attendance.
  2. Vote recorded at the meeting.
  3. Written consent obtained after the resolution.

A member’s attendance does not automatically amount to consent.

Similarly, a member who voted in favour should provide the required written consent.

12.2 What Should the Written Consent Contain?

The consent should identify:

  • Name of the society.
  • Name of the member.
  • Flat / shop number.
  • Reference to the redevelopment resolution.
  • Date of the SGM.
  • Confirmation that the member voted in favour.
  • Written consent for the society to proceed with the next prescribed redevelopment steps.
  • Signature and date.

The consent should be carefully worded so that it does not unintentionally waive the member’s existing property rights or authorise unapproved commercial terms.

The written consent at this preliminary stage should not be confused with the individual PAAA or final acceptance of the developer’s contractual terms.


13. Appointment of the Selected Architect / PMC

After the SGM selects the Architect / PMC, the Secretary must issue the appointment letter within 30 days from the date of the meeting.

The Managing Committee must also execute a written agreement with the selected professional on the terms and conditions approved at the SGM.

13.1 What Should the Appointment Letter State?

The appointment letter should identify:

  • The selected professional.
  • The SGM resolution approving the selection.
  • Scope of work.
  • Professional fees.
  • Payment milestones.
  • Time period.
  • Project-report deliverables.
  • Responsibility for technical assessment.
  • Responsibility for examining the applicable planning regulations.
  • Requirement to examine conveyance and title-related information.
  • Requirement to prepare realistic development feasibility.
  • Reporting and presentation obligations.
  • Conflict-of-interest disclosure.
  • Confidentiality and record-handling requirements.

13.2 Why Is a Written Agreement Necessary?

A written agreement avoids uncertainty about the professional’s obligations.

It should clearly distinguish the initial project-report assignment from any later appointment for tendering assistance, developer selection, construction supervision or full PMC services.

The society should not assume that all future services are automatically included in the initial professional fee.


14. Registrar’s Representative: Is Presence Required at the Initial SGM?

This question requires careful reading of the 2026 Government Order together with the Maharashtra Co-operative Societies Rules, 1961.

14.1 What Does the 2026 Government Order Say?

The Government Order specifically requires the developer-selection SGM to be conducted in the presence of the Registrar’s authorised officer.

The detailed procedure for appointment of that officer appears in Paragraph 12.

The initial redevelopment SGM under Paragraph 4 is separately described.

14.2 What Do the 2026 Housing Society Rules Say?

The Maharashtra Co-operative Societies (Amendment) Rules, 2026 introduced Chapter XI-B concerning cooperative housing societies, including Rules 106C-1 to 106C-14.

Rule 106C-13 contains provisions concerning general body meetings relating to redevelopment, including the Registrar’s representative, notice, quorum and video recording requirements.

The relevant Rules must be read together with the 2026 Government Order.

Accordingly, a society should not assume that the initial redevelopment SGM is exempt from the Registrar-representative requirement merely because Paragraph 12 of the Government Order separately describes the authorised officer for developer selection.

14.3 Practical Recommendation

Before issuing the notice for the initial redevelopment SGM, the society should obtain written clarification from the jurisdictional Registrar / Deputy Registrar regarding the required representation and the procedure for arranging it under the applicable 2026 Rules.

The society should preserve the correspondence and follow the applicable Rules as well as the specific procedure in the Government Order.

The distinction between the Registrar’s representative under the Rules and the authorised officer appointed for the developer-selection meeting should be maintained.


15. Video Recording and Preservation of Meeting Records

The 2026 Government Order and the applicable 2026 Rules contain important transparency requirements for redevelopment-related meetings.

The society should make appropriate arrangements for video recording wherever required.

The recording should be complete and should not be limited to selected portions of the meeting.

The society should preserve:

  • Original video recording.
  • Attendance sheet.
  • Virtual attendance records.
  • Meeting notice.
  • Proof of service.
  • Agenda.
  • Written suggestions.
  • Quotations received.
  • Minutes.
  • Voting records.
  • Written consents.
  • Registrar correspondence.
  • PMC appointment documents.

The video recording and supporting records should be retained in accordance with the applicable Rules and Government Order.

A society should not edit, selectively delete or otherwise alter the recording in a manner that compromises the integrity of the meeting record.


16. Important Compliance Checklist for the Initial Redevelopment SGM

The following checklist may be used by the Managing Committee and Secretary.

Before the Meeting

  • Verify the validity of the requisition.
  • Verify the number and membership status of requisitioning members.
  • Record receipt of the requisition.
  • Place the requisition before the Managing Committee within the prescribed period.
  • Examine Section 76 and the registered bye-laws.
  • Obtain at least three eligible Architect / PMC quotations.
  • Examine the Registrar-representative requirement under the 2026 Rules.
  • Fix the meeting date, time and venue.
  • Prepare a clear agenda.
  • Issue at least 14 days’ notice.
  • Preserve proof of service.
  • Inform members about the 8-day deadline for written suggestions.
  • Arrange eligible virtual participation.
  • Arrange identity and attendance verification.
  • Arrange video recording as required.

During the Meeting

  • Verify physical attendance.
  • Verify eligible virtual participants.
  • Calculate the two-thirds quorum.
  • Confirm at least 51% physical attendance.
  • Conduct the preliminary redevelopment vote.
  • Verify at least 51% approval of total membership.
  • Consider members’ suggestions and objections.
  • Record members’ views with names.
  • Select the Architect / PMC.
  • Determine scope of professional work and terms.
  • Record all resolutions and voting results.

After the Meeting

  • Prepare accurate minutes.
  • Obtain written consent from members who voted in favour.
  • Preserve attendance and voting records.
  • Preserve the video recording.
  • Complete the required Registrar communications.
  • Issue the Architect / PMC appointment letter within 30 days.
  • Execute the written professional agreement.
  • Maintain the redevelopment document file.

17. Frequently Asked Questions

1. Can the Managing Committee itself decide to redevelop the building?

The 2026 Government Order provides that the redevelopment decision is to be taken through the prescribed procedure by the duly elected and legally constituted Managing Committee and General Body. The initial decision to proceed with redevelopment must be considered and approved in the prescribed SGM with the required quorum and majority. The Managing Committee cannot unilaterally substitute its decision for the prescribed General Body process.

2. Is a requisition signed by one-fifth of the members sufficient to compel an SGM?

A valid requisition satisfying Section 76 of the MCS Act and the applicable bye-laws triggers the statutory obligation to convene the meeting. The society must verify the relevant membership count and validity of signatures.

3. Is the Secretary required to convene the meeting within one month or two months?

Section 76(1) of the MCS Act provides a one-month period following a valid requisition. Paragraph 4 of the 2026 Government Order refers to two months. This apparent difference should not be resolved by simply ignoring the statutory provision. The safer approach is to comply with the shorter statutory timeline, subject to project-specific legal advice.

4. Is 14 days’ notice mandatory?

Yes. The 2026 Government Order prescribes at least 14 days’ notice for the initial redevelopment SGM. The applicable 2026 Rules must also be followed.

5. Can a member submit written suggestions after the 8-day deadline?

Paragraph 5 provides for written suggestions at least 8 days before the meeting. The society should follow this timeline. Whether a late suggestion can be considered as a matter of discussion without affecting the prescribed procedure should be assessed according to the facts and meeting rules.

6. What is the quorum for the initial redevelopment SGM?

Two-thirds of the total membership. The number is rounded up where it results in a fraction.

7. Is 51% of the members present sufficient to approve redevelopment?

No. The initial redevelopment decision requires approval from at least 51% of the total membership, not merely 51% of the members present.

8. Can NRI members participate through video conferencing?

The 2026 Government Order expressly recognises virtual participation for members residing abroad and other specified circumstances, subject to the prescribed conditions. At least 51% of the total membership must still be physically present.

9. Can an absent member’s written consent be counted as a vote?

No. The 2026 Government Order states that the opinion or consent of absent members is not to be considered in the meeting’s decision-making process. The required approval must be established through the prescribed meeting procedure.

10. Is written consent required after the redevelopment resolution?

Yes. The Managing Committee must obtain written consent from members who voted in favour before proceeding with the next redevelopment steps.

11. Can the society appoint the PMC after the SGM without a written agreement?

The 2026 Government Order requires a written agreement with the selected Architect / PMC on the terms and conditions approved at the meeting. The appointment letter is to be issued within 30 days.

12. Must the Registrar’s representative attend the initial redevelopment SGM?

The 2026 Housing Society Rules contain redevelopment-meeting provisions concerning the Registrar’s representative. The society should examine Rule 106C-13 and obtain procedural clarification from the jurisdictional Registrar before the meeting. The specific authorised-officer procedure for developer selection under the Government Order must also be followed.

13. What happens if quorum is not present even at the adjourned meeting?

Under the 2026 Government Order, if quorum is again absent at the adjourned meeting, the meeting is cancelled and the redevelopment proposal cannot be brought again before the SGM for approval for three months.

14. Does approval of redevelopment at the initial SGM mean that the developer has been selected?

No. The initial SGM is only the preliminary decision to proceed and selection of the Architect / PMC. Developer selection takes place at a later stage after preparation of the project report and completion of the tender procedure.


18. Conclusion: A Properly Convened SGM Is the Foundation of a Lawful Redevelopment Process

The initial redevelopment SGM is more than a meeting to obtain a majority vote.

It is the formal starting point of a process that affects the society’s land, building, members’ accommodation and contractual rights.

The 2026 Government Order prescribes a detailed procedure concerning requisition, notice, professional quotations, quorum, voting, virtual participation, member suggestions and written consent.

The Managing Committee should pay particular attention to the interaction between Section 76 of the MCS Act, the 2026 Government Order and the 2026 Housing Society Rules.

A valid requisition should be handled within the applicable statutory timeline. The notice should clearly disclose the business to be transacted. The quorum and approval figures should be separately verified. Members’ views should be recorded accurately. The selected Architect / PMC should be appointed through a written and clearly defined professional engagement.

A redevelopment project should begin with an informed and properly documented decision of the society—not with an informal understanding between the Managing Committee and a prospective developer.


Related Articles in This 13-Part Redevelopment Guide

  1. Part 1: Housing Society Redevelopment in Maharashtra: The Complete Step-by-Step Roadmap
  2. Part 2: 2019 vs 2026 Government Order: What Has Changed in Maharashtra Housing Society Redevelopment?
  3. Part 3: Before You Begin: Legal, Structural and Financial Checks Before Housing Society Redevelopment
  4. Part 4: Special General Body Meeting for Redevelopment: Notice, Quorum, Voting and Legal Requirements
  5. Part 5: Role of Architect and PMC in Housing Society Redevelopment
  6. Part 6: Tender Process for Housing Society Redevelopment: Rules, Transparency and Developer Offers
  7. Part 7: Developer Selection in Housing Society Redevelopment: Registrar’s Authorised Officer and Voting Procedure
  8. Part 8: Developer Due Diligence: How a Housing Society Should Verify a Redeveloper
  9. Part 9: Development Agreement and PAAA: Protecting Members’ Rights in Redevelopment
  10. Part 10: From Demolition to Possession: Construction, Approvals and Handover
  11. Part 11: Self-Redevelopment and Group Redevelopment in Maharashtra
  12. Part 12: Dissenting, Absent, Deceased and NRI Members in Housing Society Redevelopment
  13. Part 13: Housing Society Redevelopment FAQs, Legal Checklist and Glossary
  14. Download Maharashtra Government GR सगृयो-2026/प्र.क्र.108/14-स for Re-Development dated 30/09/2026

About Advocate Ketan Palshikar

Advocate Ketan Palshikar practises in Pune, Maharashtra, with a focus on property documentation, conveyancing, title verification and legal due diligence.

For housing societies considering redevelopment, legal assistance in reviewing society resolutions, title documents, PMC engagements, tender conditions, Development Agreements and Permanent Alternate Accommodation Agreements can help protect the society’s and members’ legal interests.

For professional assistance relating to property documentation and redevelopment agreements, contact Advocate Ketan Palshikar and Associates, Pune.


Legal Disclaimer

This article is intended for general legal information and educational purposes. It is based on the Maharashtra Government Order dated 30 September 2026, the Maharashtra Co-operative Societies Act, 1960 and the applicable housing society rules as understood on 14 November 2026.

The precise procedure may depend on the society’s registered bye-laws, membership position, the validity of the requisition, applicable statutory amendments, the jurisdictional Registrar’s directions and the facts of the particular redevelopment proposal.

The apparent difference between the one-month period under Section 76 and the two-month period in Paragraph 4 of the 2026 Government Order should be examined carefully before convening the meeting.

This article should not be treated as a substitute for project-specific legal advice.