Part 2 of 13 · Redevelopment Guide for Housing Societies (Pune & PCMC)

By Advocate Ketan Palshikar | Last updated: 14 November 2026 | Based on Government Order No. SGHYO-2026/CR-108/14-S dated 30 September 2026


Introduction: A New Regulatory Framework for Housing Society Redevelopment

The Government of Maharashtra has introduced a revised procedural framework for cooperative housing society redevelopment through its Government Order dated 30 September 2026, issued under Section 79A of the Maharashtra Co-operative Societies Act, 1960.

The new Government Order, bearing reference No. SGHYO-2026/CR-108/14-S, supersedes the earlier Government Resolution dated 4 July 2019, bearing reference No. SGHYO-2018/CR-85/14-S, together with the subsequent circulars issued under the 2019 framework.

The 2026 Government Order is not merely a revision of a few procedural timelines. It changes several important aspects of the redevelopment process, including member participation, virtual attendance, preparation and approval of tender documents, developer selection, document inspection, bank guarantee, execution of individual Permanent Alternate Accommodation Agreements and accountability of office bearers.

For housing societies considering redevelopment, understanding these changes is essential.

A society should not continue following the 2019 procedure merely because it was followed in earlier redevelopment projects. The applicable process must be examined with reference to the 2026 Government Order, the Maharashtra Co-operative Societies Act and Rules, the applicable development regulations and other prevailing laws.

This article compares the two Government Orders and explains the practical consequences of the changes for managing committees, society members and developers.

1. The Two Government Orders: Basic Details

Particulars2019 Government Resolution2026 Government Order
Date4 July 201930 September 2026
ReferenceSGHYO-2018/CR-85/14-SSGHYO-2026/CR-108/14-S
Issuing DepartmentCo-operation, Marketing and Textiles DepartmentCo-operation Department
Legal AuthoritySection 79A, Maharashtra Co-operative Societies Act, 1960Section 79A, Maharashtra Co-operative Societies Act, 1960
Main purposePrescribed redevelopment procedure for cooperative housing societiesRevised procedure emphasising transparency, member participation and accountability
Current statusSuperseded by the 2026 Government OrderCurrent redevelopment directions as on 14 November 2026

1.1 Does the 2026 Government Order Replace Only the 2019 Resolution?

The preamble to the 2026 Government Order expressly states that the Government Resolution dated 4 July 2019 and all subsequent circulars issued under it in relation to redevelopment are superseded.

Accordingly, the 2019 framework should be treated as historical reference material rather than the operative procedural framework for new redevelopment decisions.

However, this does not mean that the 2026 Government Order replaces the entire legal framework governing cooperative housing societies.

The following continue to operate independently, subject to their amendments and applicability:

  • Maharashtra Co-operative Societies Act, 1960.
  • Maharashtra Co-operative Societies Rules, 1961, including applicable amendments.
  • Registered bye-laws of the society, to the extent consistent with applicable law.
  • Applicable Development Control Regulations and UDCPR.
  • Real Estate (Regulation and Development) Act, 2016.
  • Registration Act, 1908.
  • Maharashtra Stamp Act.
  • Other applicable laws, regulations and directions.

The 2026 Government Order must therefore be read together with these legal instruments.

1.2 What About Redevelopment Projects Already Underway?

The 2026 Government Order supersedes the 2019 framework but does not expressly set out a detailed transitional mechanism for every category of ongoing redevelopment project.

Therefore, it would be unsafe to state that every step already completed under the 2019 procedure automatically becomes invalid, or that every ongoing project must restart from the beginning.

The position should be examined project by project, considering:

  • The date of the initial redevelopment resolution.
  • The stage at which the society had reached on 30 September 2026.
  • Whether the developer had already been selected.
  • Whether the Development Agreement had been executed and registered.
  • Whether individual PAAA had been executed.
  • Whether statutory approvals had been obtained.
  • Whether any third-party rights had been created.
  • Whether a court or competent authority has passed an order affecting the project.

Where a material procedural step remains pending, the society should obtain specific legal advice on the applicability of the new directions before proceeding.


2. Summary of the Major Changes: 2019 vs 2026

The following table identifies the principal changes introduced by the 2026 Government Order.

Subject2019 Framework2026 FrameworkPractical Significance
Scope of redevelopmentDeveloper-led, self and group redevelopmentExpressly covers the same broad categories and applies the developer-selection procedure, with adaptation, to contractor appointment in self-redevelopmentClarifies application to different redevelopment models
Requisition for SGMAt least 1/5 membersAt least 1/5 membersBasic threshold retained
Initial SGM notice14 days14 daysNo change
Initial SGM quorum2/3 of total membership2/3 of total membershipNo change in basic threshold
Initial redevelopment approvalAt least 51% of total membershipAt least 51% of total membershipThreshold retained; eligible virtual participation newly recognised subject to physical attendance condition
Virtual attendanceNo corresponding express provision in the 2019 GRPermitted for specified members and circumstances, subject to conditionsEnables eligible members to participate remotely
Member suggestionsWritten suggestions could be submitted before the meetingWritten suggestions may be submitted at least 8 days before the meetingSpecific submission timeline
PMC selectionAt least 3 quotations and selection at SGMBroadly retainedGreater emphasis on defined professional scope and project reporting
Project reportFSI/TDR and redevelopment feasibilityExpanded assessment of applicable planning rules and scheme-wise comparative reportsMore comprehensive feasibility assessment
Committee meeting after project reportNo comparable specific 30-day timelineWithin 30 days of receiving the reportDefined review timeline
Tender draftFinalised by Managing CommitteeTo be placed before and approved by the General BodyGreater member involvement
Tender publicationNewspaper advertisementMarathi and English advertisements in highest-circulation local newspapersMore explicit publication requirement
First tender extensionAt least 7 daysAt least 15 daysMore time to attract tenders
Second tender extension7 days1 weekSubstantially retained
Appointment of Registrar’s authorised officerNo express 14-day decision timelineRegistrar to decide appointment within 14 days of receiving the prescribed proposalDefined administrative timeline
Developer selection2/3 quorum and 51% total membership approvalSame basic thresholds, with eligible virtual participation subject to physical attendance conditionMore inclusive but controlled participation
Secret ballotNo comparable express provisionAvailable if at least 1/5 members request it in writingFormal voting safeguard
Developer’s MahaRERA track recordAt least one project registered with MahaRERA was specifiedThe same specific eligibility condition is not repeated in the 2026 orderIndependent developer due diligence remains essential
Redevelopment websiteExpress website requirementNo equivalent express website requirement; document inspection rights are providedDifferent information-access mechanism
Member inspection of documentsWebsite-based access and prescribed communicationFree inspection of redevelopment documents; copies on payment of prescribed chargesDirect access to records
Development Agreement approvalManaging Committee approvalGeneral Body approvalGreater member-level control over the contract
Bank guarantee20% of total redevelopment project costGeneral Body decides proportion and formFixed percentage replaced by a General Body decision
PAAA timelineNo equivalent specific three-month deadlineWithin 3 months after registration of Development AgreementDefined timeline for individual agreements
New membershipAdmission after project completion with General Body approvalMembership applications to be decided within 3 months after possessionDefined post-possession timeline
Dispute resolution clauseSpecific reference to Section 91Reference to competent court / authority under prevailing lawWider drafting flexibility, subject to actual jurisdiction
Flat allocationAfter OC; floor-wise where possible and lottery where required, with Registrar representative and video recordingSGM-based allocation; floor-wise where feasible or lottery where necessary, with video recording and prescribed reportingMore detailed General Body-led allocation process
AccountabilitySection 79A(3) operated under the ActExpress warning of action under Sections 79A(3) / 78A for specified violations and prejudicial conductGreater emphasis on accountability

The detailed differences are explained below.


3. Eligibility and Scope of Redevelopment

3.1 Building Eligibility

The 2019 and 2026 frameworks both contemplate redevelopment where the competent authority has declared the building to be dangerous, dilapidated or otherwise unsafe in the manner specified in the applicable Government Order, and the building is eligible under the applicable development regulations.

The 2026 Government Order does not create an unrestricted right to redevelop every old building merely because of its age.

The society must examine both:

  1. The condition of the building and the relevant declaration by the competent authority; and
  2. Eligibility under the applicable Development Control Regulations.

3.2 Scope of Application

Both frameworks cover redevelopment through a developer, self-redevelopment and group redevelopment.

The 2026 Government Order expressly clarifies that the prescribed developer-selection procedure also applies, with necessary adaptation, to the appointment of a contractor in self-redevelopment.

Practical implication: A society cannot assume that self-redevelopment is outside the procedural safeguards prescribed for developer selection merely because it is appointing a contractor instead of a conventional developer.


4. Requisition for Special General Body Meeting: No Change in the Basic Threshold

Under both the 2019 and 2026 frameworks, at least one-fifth of the society’s members may submit a written requisition seeking a Special General Body Meeting to consider redevelopment.

The 2026 Government Order specifies that:

  • The Managing Committee should take note of the requisition within 8 days.
  • The Secretary should convene the meeting within 2 months under the wording of the Government Order.
  • Members should receive at least 14 days’ notice.
  • Proof of service should be preserved.

The basic one-fifth requisition threshold and 14-day notice requirement are retained.

Important statutory qualification: Section 76 of the MCS Act

Section 76 of the Maharashtra Co-operative Societies Act contains a separate statutory requirement concerning the period for convening a Special General Meeting following a valid requisition.

The two-month period stated in the 2026 Government Order should not be read in isolation from the parent Act. The society must examine the statutory one-month requirement under Section 76 and the applicable legal position before fixing the meeting date.

A Government Order issued under Section 79A should not casually be treated as overriding a statutory provision.

Practical recommendation: The Managing Committee should take legal advice immediately upon receiving the requisition and should endeavour to comply with the shorter statutory period wherever Section 76 applies.

This issue is particularly important because an improperly convened meeting may expose the society’s subsequent redevelopment decisions to challenge.


5. Quorum and 51% Approval: The Threshold Has Not Changed

One of the most misunderstood aspects of the 2026 Government Order is the requirement of 51% approval.

The 2019 framework already required:

  • Quorum of two-thirds of the total membership; and
  • Approval of at least 51% of the total membership for the initial redevelopment decision.

The 2026 framework retains these basic numerical requirements.

Therefore, it is incorrect to state that the 51% approval requirement was introduced for the first time in 2026.

The important change is the recognition of eligible virtual participation, subject to a mandatory physical-attendance condition.

5.1 Example: Society Having 100 Members

Under both frameworks:

  • Total membership: 100.
  • Two-thirds quorum: 67 members, after rounding up.
  • Required approval: at least 51 members.

The 51% requirement is calculated with reference to the total membership, not merely the number of members present.

For example, if 67 members attend, at least 51 must support the proposal.

If 75 members attend, at least 51 must still support it.

The 2026 Government Order itself provides an example to this effect.

5.2 What Has Changed in 2026?

The 2026 Government Order permits specified members who cannot attend physically to participate through a remote system or Video Conferencing.

The specified circumstances include:

  • Members residing abroad.
  • Members who are seriously ill.
  • Members with disabilities.
  • Members unable to attend physically for other unavoidable reasons.

Such eligible virtual attendance is recognised for quorum and the 51% approval calculation.

However, the Government Order also requires at least 51% of the total membership to be physically present.

Thus, in a society of 100 members:

  • At least 67 members must participate to satisfy the two-thirds quorum.
  • At least 51 members must be physically present.
  • Eligible virtual participants may be counted for quorum and the approval requirement.
  • At least 51 members must support the proposal.

The society must maintain separate records of physical attendance, virtual attendance and votes.

5.3 What Happened Under the 2019 Framework?

The 2019 Government Resolution did not contain the corresponding express virtual participation mechanism for these redevelopment meetings.

The 2026 provision is therefore a significant procedural change, particularly for societies having NRI members, senior citizens, persons with disabilities and members facing unavoidable attendance difficulties.


6. Written Suggestions and Written Consent: More Clearly Structured Participation

The 2019 framework already recognised member participation and required written consent from members who voted in favour of the initial redevelopment resolution.

The 2026 Government Order retains the written-consent requirement but sets out the member participation process more clearly.

6.1 Written Suggestions Before the Initial SGM

Under the 2026 Government Order, members may submit their realistic plans, suggestions and recommendations in writing at least 8 days before the meeting.

The society should preserve these submissions and ensure that the relevant suggestions are placed before the meeting.

6.2 Recording Opinions in the Minutes

The 2026 Government Order specifically requires the views and suggestions expressed by members to be recorded in the meeting minutes with their names.

It also states that opinions or consents of absent members are not to be considered as part of the meeting’s decision-making process merely because they are communicated in writing, orally or otherwise.

This is important because the redevelopment resolution must reflect the actual decision of members participating in the meeting under the prescribed procedure.

6.3 Written Consent After the Initial Resolution

Once the preliminary redevelopment resolution is passed, the Managing Committee must obtain written consent from members who voted in favour before proceeding further.

This requirement was also present in the 2019 framework. It has not been introduced for the first time in 2026.

The society should distinguish between:

  • Attendance at the meeting.
  • Vote recorded in favour.
  • Written consent obtained after the resolution.

These are related but separate records.


7. Appointment of Architect / PMC and Preparation of the Project Report

The requirement to obtain at least three quotations and select an Architect / PMC at the initial Special General Body Meeting existed under the 2019 framework and is retained in 2026.

However, the 2026 Government Order places greater emphasis on the content of the project report and the process for reviewing it.

7.1 Scope of the Project Report

Under the earlier framework, the Architect / PMC was required to examine the building and land, conveyance status, available FSI and TDR, and prepare a project report.

The 2026 framework expands the expected assessment.

The PMC must consider the rules applicable to the land and planning authority, including the relevant framework of authorities such as MHADA, CIDCO, SRA, MMRDA and municipal corporations, depending on the property.

The report must consider:

  • Available FSI.
  • Available TDR.
  • Applicable Development Control Regulations.
  • Residential and commercial areas.
  • Open spaces.
  • Gardens.
  • Parking.
  • Construction specifications.
  • Member requirements.
  • Benefits available under different applicable schemes.

Where different development schemes are available, separate scheme-wise reports and a comparative statement are contemplated.

7.2 New 30-Day Timeline for Committee Review

The 2026 Government Order specifically requires the Secretary to convene a Managing Committee meeting within 30 days after receipt of the project report.

The PMC should be invited to explain the report.

The report must be made available for inspection by members, and their comments are to be invited within the prescribed process.

This defined review timeline was not stated in the same manner under the 2019 framework.

7.3 Practical Significance

The project report is the foundation for the tender process.

If the report is incomplete or based on unrealistic FSI assumptions, the tender may invite offers that are commercially attractive but legally or technically unworkable.

The expanded 2026 reporting requirements are intended to facilitate a more informed decision before the society commits to tender conditions.


8. Approval of the Tender Draft: A Significant Change in Member Participation

This is one of the important procedural changes introduced by the 2026 Government Order.

Under the 2019 Framework

The Managing Committee was responsible for finalising the draft tender after considering the project report and relevant recommendations.

Under the 2026 Framework

The draft tender must be placed before the General Body for approval.

The 2026 Government Order also requires the tender process to be supported by publication of advertisements in Marathi and English newspapers having the highest circulation in the relevant local area.

Why Is This Important?

The tender document determines the commercial and technical terms on which developers will compete.

It may include:

  • Additional carpet area.
  • Corpus.
  • Transit rent.
  • Deposit.
  • Shifting charges.
  • Construction specifications.
  • Completion period.
  • Bank guarantee.
  • Developer eligibility.
  • Technical and financial conditions.
  • Contractual safeguards.

When the General Body approves the tender draft, members have a more direct role in determining the terms on which their society’s redevelopment will be offered to developers.

8.1 The Fixed Variable Principle

The 2026 Government Order requires the society to keep either the additional carpet area or the corpus fund constant for comparison, while evaluating the other commercial terms.

For example, if additional carpet area is fixed as the non-variable factor, developers may compete on corpus and other eligible commercial terms.

Alternatively, if corpus is fixed, additional carpet area and other permissible terms may be compared.

This is intended to make the offers more comparable and reduce the risk of misleading comparisons.

The society should ensure that the tender conditions clearly state the chosen basis of comparison.


9. Tender Extensions: The First Extension Has Increased to 15 Days

The minimum number of tenders contemplated under both frameworks is three.

The difference lies in the extension period where fewer than three tenders are received.

Situation2019 Framework2026 Framework
Minimum tenders33
First extensionAt least 7 daysAt least 15 days
Second extension7 days1 week
Fewer than 3 tenders even after extensionsAvailable tenders may be placed before the SGMAvailable tenders may be placed before the SGM

Practical Significance

The first extension has been increased from at least one week to at least 15 days.

This gives additional time for interested developers to prepare and submit their offers.

However, the society should not treat the receipt of fewer than three tenders as an automatic reason to cancel the redevelopment proposal.

The Government Order permits the available tenders to be placed before the General Body after following the prescribed extensions.

The PMC should prepare the comparative statement and explain the technical and financial merits of the available offers.


10. Developer Selection: A More Detailed and Controlled Procedure

Both the 2019 and 2026 frameworks require developer selection through a Special General Body Meeting in the presence of the Registrar’s authorised officer.

However, the 2026 Government Order introduces more specific timelines and procedural safeguards.

10.1 Appointment of the Authorised Officer

Under the 2019 framework, the Managing Committee was required to apply to the Registrar for appointment of an authorised officer. The 2019 order did not prescribe the same specific 14-day decision timeline now found in the 2026 framework.

The 2026 Government Order requires the Registrar to decide the appointment of the authorised officer within 14 days of receiving the prescribed proposal and supporting documents.

This is a procedural improvement because it establishes a defined timeline for the administrative step.

10.2 Notice for Developer-Selection Meeting

After appointment of the authorised officer, the Secretary must convene the developer-selection SGM within the period prescribed in the 2026 Government Order.

The meeting notice must be served at least 14 days in advance and must include the comparative statement.

The society should preserve proof of service and all supporting documents.

10.3 Quorum and Approval

The basic requirements of:

  • Two-thirds quorum; and
  • At least 51% approval of total membership

were present under the 2019 framework and are retained in 2026.

The 2026 framework additionally recognises eligible virtual participation, subject to the physical-attendance condition.

10.4 Secret Ballot

The 2026 Government Order expressly provides that voting may be conducted by show of hands or by secret ballot if at least one-fifth of the total membership requests it in writing.

This is an important procedural safeguard.

The authorised officer is responsible for arranging the prescribed voting procedure, including arrangements for eligible virtual participants, where applicable.

The 2019 framework did not contain the same express secret-ballot mechanism.

10.5 Identity Verification

The 2026 framework contains detailed requirements for verifying the identity of members attending the developer-selection meeting.

Members must attend in their individual capacity and carry valid identification.

The prescribed verification should be carried out with reference to the society’s membership records and relevant documents.

A person should not be allowed to participate as a proxy merely to substitute for an actual member where the Government Order requires personal participation.

10.6 Video Recording

Video recording of the developer-selection meeting was contemplated under the 2019 framework as well.

Therefore, it would be incorrect to describe video recording of developer selection as an entirely new requirement introduced for the first time in 2026.

The 2026 framework provides a more detailed procedural structure around the meeting, including attendance, identity verification, voting and submission of records.

10.7 Submission of Records to the Registrar

The 2026 Government Order specifies the documents and records to be submitted to the Registrar after the developer-selection meeting.

These include the relevant minutes, member approvals, developer consent and attendance records, together with the authorised officer’s report and prescribed video-recording material.

The society should ensure that the records are complete, properly certified where required and submitted within the prescribed period.


11. Developer’s MahaRERA Track Record: An Important Difference

The 2019 Government Resolution expressly required the selected developer or its associates / collaborators to have at least one project registered with MahaRERA.

The 2026 Government Order does not repeat this specific eligibility condition in the same form.

This is a difference between the two Government Orders.

However, this should not be misunderstood to mean that RERA has become irrelevant to redevelopment.

There are two separate issues:

  1. Whether the developer satisfies the specific developer-selection condition under the Government Order; and
  2. Whether the proposed redevelopment project or its sale component requires registration under the Real Estate (Regulation and Development) Act, 2016.

The second issue continues to be governed by RERA and applicable MahaRERA directions.

The society should independently verify:

  • Developer’s track record.
  • Existing MahaRERA projects.
  • Completion status.
  • Pending complaints.
  • Regulatory actions.
  • Project registration requirements.
  • Financial and technical capability.

The absence of the earlier express track-record condition does not make developer due diligence optional.


12. Redevelopment Website and Access to Documents: A Change in the Information-Access Mechanism

Under the 2019 Framework

The society was expressly required to create an internet website for the redevelopment project.

The website was intended to provide members with access to redevelopment-related information, including:

  • Notices.
  • Meeting minutes.
  • Project reports.
  • Other redevelopment documents.

The 2019 framework also contemplated communication of relevant information to members by email, in person or registered post.

Under the 2026 Framework

The 2026 Government Order does not repeat the same express requirement to create a dedicated redevelopment website.

Instead, it provides for inspection of redevelopment-related documents by members.

The relevant records must be made available for free inspection, and copies may be provided on payment of the prescribed charges.

The documents include redevelopment-related records such as tenders, reports, agreements and other relevant material.

Practical Significance

The change is in the prescribed information-access mechanism.

A society should not assume that the absence of an express website requirement permits it to withhold redevelopment documents from members.

The right to inspect relevant records remains an important part of the revised framework.

Should a Society Still Maintain a Website?

A dedicated website or secure digital document repository may continue to be useful as a transparency and record-management measure.

However, the society should distinguish between:

  • A legal requirement expressly imposed by the 2026 Government Order; and
  • A recommended administrative practice adopted to improve communication.

A website may be a good governance measure, but it should not be represented as an express mandatory condition under the 2026 order merely because it was required under the earlier framework.


13. Development Agreement: General Body Approval Is Now Specifically Required

This is one of the most significant contractual changes.

Under the 2019 Framework

The Development Agreement was to be executed by the Managing Committee on the terms and conditions approved through the prescribed process, with the PMC’s guidance.

Under the 2026 Framework

The 2026 Government Order specifically requires the Development Agreement to be subject to the terms and conditions approved by the General Body.

This strengthens the role of the members in approving the principal redevelopment contract.

Why Is This Important?

The Development Agreement is the central document governing the relationship between the society and developer.

It determines:

  • Development rights.
  • Existing members’ rehabilitation entitlement.
  • Additional carpet area.
  • Corpus.
  • Rent and transit accommodation.
  • Bank guarantee.
  • Construction period.
  • Specifications.
  • Developer’s obligations.
  • Restrictions on transfer of development rights.
  • Default and termination.
  • Indemnity and dispute-resolution provisions.

A society should not treat approval of the developer as an unrestricted authority to execute any Development Agreement subsequently prepared by the developer.

The agreement must be consistent with the General Body-approved terms and conditions.

Practical Recommendation

Before the Development Agreement is placed for approval, members should be given an opportunity to understand its material commercial and legal terms.

The final agreement should be vetted by an independent legal professional acting in the society’s interest.

The PMC should assist with technical and project-related terms, but technical assistance should not replace legal scrutiny of the contractual rights and liabilities.


14. Bank Guarantee: The Fixed 20% Requirement Has Been Replaced

One of the most important financial changes concerns the bank guarantee.

Under the 2019 Framework

The developer was required to provide a bank guarantee equivalent to 20% of the total redevelopment project cost.

This was a specifically stated contractual requirement under the 2019 Government Resolution.

Under the 2026 Framework

The 2026 Government Order provides that the General Body must decide:

  • The proportion of the total redevelopment project cost for which a bank guarantee is to be provided; and
  • The form in which the guarantee is to be provided.

Therefore, the 2026 Government Order does not prescribe the same fixed 20% requirement as a universal mandatory percentage.

Does This Mean the Society Can Accept a Lower Bank Guarantee?

The society may determine the amount and form with General Body approval, but that does not mean it should accept inadequate security.

The bank guarantee is an important safeguard against risks such as:

  • Developer default.
  • Abandonment of the project.
  • Failure to complete construction.
  • Failure to meet contractual milestones.
  • Financial distress.
  • Failure to honour agreed obligations.

The General Body should consider the total project cost, developer’s financial strength, project duration, construction risks and the potential cost of protecting members if the project fails.

What Should the Society Examine?

The Development Agreement should clearly address:

  1. Amount of the bank guarantee.
  2. Issuing bank and acceptability of the guarantee.
  3. Validity period.
  4. Renewal obligations.
  5. Conditions for invocation.
  6. Events of default.
  7. Claim period.
  8. Reduction or release conditions.
  9. Consequences of failure to renew.
  10. Whether the guarantee remains adequate throughout the relevant project period.

A bank guarantee that expires before the developer completes the project may provide little practical protection.

Practical recommendation: The society should determine the security requirement through independent financial and legal advice rather than selecting a percentage merely because it is offered by the developer.


15. Permanent Alternate Accommodation Agreement: A New Three-Month Timeline

Both the 2019 and 2026 frameworks require the Development Agreement and individual Permanent Alternate Accommodation Agreements to be registered under the Registration Act, 1908.

However, the 2019 Government Resolution did not prescribe the same express three-month timeline for executing individual PAAA after registration of the Development Agreement.

The 2026 Government Order now provides that individual PAAA must be executed within three months after registration of the Development Agreement.

Why Is This Change Important?

The Development Agreement records the overall arrangement between the society and developer.

The PAAA records the individual member’s permanent rehabilitation entitlement.

The PAAA should clearly identify:

  • Existing premises.
  • New premises entitlement.
  • RERA carpet area.
  • Flat allocation, where determined.
  • Parking, where applicable.
  • Amenities and specifications.
  • Rent and transit accommodation.
  • Corpus and other benefits.
  • Possession timeline.
  • Rights and obligations of the parties.

The three-month timeline encourages the society and developer to document each member’s entitlement without unnecessary delay.

When Can Members Vacate?

The 2026 Government Order retains the important protection that members should vacate only after all required legal approvals have been obtained and individual PAAA have been registered.

Members should not surrender possession merely because the developer has been selected or the Development Agreement has been signed.

The society should ensure that the contractual and statutory conditions are satisfied before asking members to vacate.


16. Admission of New Members After Redevelopment

The 2019 framework contemplated admission of new members after completion of the redevelopment project, subject to General Body approval.

The 2026 Government Order changes the approach.

It provides that after completion / possession, the society’s Managing Committee must decide applications for membership from new flat or premises holders within three months and issue membership and share certificates as applicable.

Practical Significance

This introduces a defined timeline for dealing with membership applications after possession.

The society should prepare in advance for:

  • Updating the membership register.
  • Examining membership applications.
  • Verifying relevant documents.
  • Issuing share certificates.
  • Updating the society’s records.
  • Recording the new premises and member details.

The society should also distinguish between the legal title to a premises and membership of the cooperative society. Membership records should be maintained in accordance with the Act, Rules and applicable bye-laws.


17. Dispute Resolution: The Specific Section 91 Reference Has Changed

Under the 2019 Framework

The Development Agreement was required to contain a provision referring redevelopment disputes to the mechanism under Section 91 of the Maharashtra Co-operative Societies Act.

Under the 2026 Framework

The new Government Order refers more generally to approaching the competent court or authority under the applicable prevailing law.

Does This Mean Section 91 No Longer Applies?

No.

The change in wording of the Government Order does not repeal or override Section 91 of the MCS Act.

Whether a particular dispute falls within the jurisdiction of the Co-operative Court depends on the nature of the dispute, the parties, the statutory provisions and applicable judicial decisions.

Similarly, a dispute involving contractual rights, title, third-party claims, RERA obligations or other statutory remedies may require a separate jurisdictional analysis.

The society should not assume that every redevelopment dispute must necessarily be referred to one forum merely because the parties have inserted a general dispute-resolution clause in the Development Agreement.

Practical Recommendation

The Development Agreement should contain a carefully drafted dispute-resolution provision that recognises the jurisdiction of the competent court, tribunal or authority under the applicable law.

A contractual clause cannot confer jurisdiction on a forum where the statute does not provide it.


18. Flat Allocation in the Redeveloped Building: A More Detailed General Body Process

Both frameworks recognise floor-wise allotment, where feasible, and lottery where necessary.

However, the 2026 Government Order provides a more detailed General Body-led process.

Under the 2019 Framework

Flat allocation was contemplated after obtaining the Occupation Certificate.

Where possible, allocation was to follow the existing floor-wise position. If a lottery was necessary, it was to be conducted by the developer in the presence of the Registrar’s representative, with video recording.

Under the 2026 Framework

The revised process provides for:

  • A Special General Body Meeting.
  • At least 14 days’ notice to members.
  • Approval by the prescribed majority.
  • Floor-wise allocation as far as practicable.
  • Lottery where necessary.
  • Video recording of the meeting.
  • Submission of minutes, video recording and certified allotment list to the Registrar within the prescribed period.

Practical Significance

Flat allocation directly affects members’ rehabilitation rights.

The society should ensure that the allocation process is transparent and consistent with the Development Agreement and individual PAAA.

The allocation procedure should not become an opportunity to alter the agreed entitlement of any member.


19. Committee Members and Office Bearers: Restriction on Developer Relationship

Both the 2019 and 2026 frameworks contain a restriction intended to prevent a society’s committee member or office bearer, or their relative, from being the developer.

The 2026 Government Order retains this restriction.

The objective is to avoid conflicts of interest and protect the integrity of the redevelopment process.

The society should carefully examine any potential conflict of interest involving:

  • Committee members.
  • Office bearers.
  • Their relatives.
  • Entities in which they have an interest.
  • Developers and associated entities.

A transparent disclosure process is important even where the society believes that no actual conflict exists.


20. Accountability for Violations: Express Reference to Sections 78A and 79A(3)

The 2026 Government Order specifically states that where its directions are violated, or where collusion, fraud, misleading conduct or acts prejudicial to members’ interests are found in the redevelopment process, the responsible office bearers or committee members may be liable for action under Sections 79A(3) and 78A of the MCS Act.

Was There No Accountability Under the 2019 Framework?

It would be incorrect to suggest that the 2019 framework operated without any statutory accountability.

Section 79A(3) of the MCS Act already provided statutory consequences for non-compliance with directions issued under Section 79A.

The important change is that the 2026 Government Order expressly highlights the possibility of action against responsible office bearers and committee members for specified violations and conduct prejudicial to members’ interests.

Practical Significance

Managing Committee members should maintain proper records of:

  • Notices and proof of service.
  • Attendance sheets.
  • Meeting minutes.
  • Voting records.
  • Written consents.
  • PMC appointment and agreements.
  • Project reports.
  • Tender documents.
  • Comparative statements.
  • Developer due diligence.
  • General Body approvals.
  • Development Agreement and PAAA.
  • Registrar correspondence.
  • Construction and possession records.

A committee member should not assume that a General Body resolution automatically protects them from liability if the process involves fraud, collusion, misrepresentation or violation of mandatory directions.

At the same time, the reference to Sections 78A and 79A(3) does not mean that every procedural error automatically results in removal or other action. The statutory requirements, competent authority’s powers and applicable procedure must be followed.


21. Which Requirements Have Not Changed?

It is equally important to identify provisions that were retained.

The following requirements were already present under the 2019 framework and continue in the 2026 framework, subject to the revised details:

  1. At least one-fifth of members may requisition an SGM.
  2. The initial SGM requires 14 days’ notice.
  3. The redevelopment SGM requires two-thirds quorum.
  4. At least 51% of total membership must support the initial redevelopment decision.
  5. Members voting in favour must provide written consent before further steps.
  6. At least three quotations are required for selecting the Architect / PMC.
  7. The PMC must prepare the project report within the prescribed two-month period.
  8. The tender process ordinarily seeks at least three tenders.
  9. Developer selection takes place through an SGM in the presence of the Registrar’s authorised officer.
  10. Developer selection requires two-thirds quorum and at least 51% approval of total membership.
  11. The Development Agreement and PAAA must be registered.
  12. Members should vacate only after the required approvals and registration of individual PAAA.
  13. The developer’s development rights are non-transferable.
  14. The redevelopment project is ordinarily to be completed within two years, with an exceptional extension up to three years.
  15. The project must provide for alternative accommodation, rent or transit accommodation.
  16. Floor-wise allotment is preferred where feasible, with lottery where necessary.
  17. A committee member or office bearer, or their relative, cannot be the developer.

The 2026 Government Order therefore does not discard the entire 2019 procedure. It retains several foundational safeguards while modifying and expanding other aspects.


22. What Should Housing Societies Do Now?

Societies planning redevelopment should review their internal procedures and documents in light of the 2026 Government Order.

The following action points may be used as an initial compliance checklist.

For Societies That Have Not Yet Started Redevelopment

  • Obtain the current Government Order and applicable legal materials.
  • Verify the Managing Committee’s legal constitution.
  • Examine building eligibility and land title.
  • Review conveyance status.
  • Obtain preliminary structural and development feasibility advice.
  • Follow the revised SGM procedure.
  • Obtain at least three eligible Architect / PMC quotations.
  • Ensure the project report addresses applicable development regulations.
  • Place the draft tender before the General Body for approval.
  • Follow the revised tender extension periods.
  • Arrange the developer-selection meeting in the prescribed manner.
  • Consider secret-ballot requirements.
  • Conduct independent developer due diligence.
  • Obtain General Body approval of the Development Agreement.
  • Determine an adequate bank guarantee.
  • Execute and register individual PAAA within the prescribed timeline.
  • Ensure that members do not vacate before the required approvals and registered PAAA.
  • Maintain complete records throughout the project.

For Societies Where Redevelopment Is Already Underway

  • Identify the stage reached before 30 September 2026.
  • Review the validity of resolutions already passed.
  • Examine the tender and developer-selection records.
  • Review whether the Development Agreement has been approved and registered.
  • Check whether individual PAAA have been executed.
  • Review the bank guarantee and transit accommodation arrangements.
  • Identify pending steps that may be affected by the new framework.
  • Obtain project-specific legal advice on transitional issues.

A society should not restart or disregard completed steps without examining the legal consequences and existing contractual rights.


23. Frequently Asked Questions

1. Has the 2026 Government Order completely replaced the 2019 Government Resolution?

Yes. The preamble to the 2026 Government Order expressly supersedes the 4 July 2019 Government Resolution and subsequent circulars issued under it in relation to redevelopment. However, the MCS Act, Rules, applicable bye-laws and other laws continue to operate.

2. Was the 51% approval requirement introduced in 2026?

No. The requirement of approval from at least 51% of the total membership existed under the 2019 framework. The 2026 Government Order retains it and introduces eligible virtual participation subject to the physical-attendance requirement.

3. Can NRI members participate virtually in redevelopment meetings?

The 2026 Government Order permits virtual participation for specified members and circumstances, including members residing abroad. The participation must comply with the prescribed conditions, including the mandatory physical attendance threshold.

4. Is a 20% bank guarantee still compulsory?

The 2019 Government Resolution prescribed a bank guarantee equivalent to 20% of the total redevelopment project cost. The 2026 Government Order replaces this fixed percentage with a General Body decision on the proportion and form of the bank guarantee.

5. Must the General Body approve the tender document?

Yes. The 2026 Government Order requires the draft tender to be placed before the General Body for approval. This is a significant change from the earlier framework, under which the Managing Committee finalised the draft tender.

6. Is a secret ballot mandatory for developer selection?

Not automatically. Under the 2026 Government Order, voting may be by show of hands or by secret ballot if at least one-fifth of the total membership requests it in writing.

7. Is a dedicated redevelopment website still compulsory?

The 2026 Government Order does not repeat the express website requirement contained in the 2019 framework. However, members are entitled to inspect redevelopment-related documents under the revised procedure. A website or secure digital repository may still be useful as a good governance measure.

8. Does the developer still need to have at least one MahaRERA-registered project?

The specific developer-eligibility condition requiring at least one project registered with MahaRERA, which appeared in the 2019 framework, is not repeated in the same form in the 2026 Government Order. However, independent developer due diligence and compliance with applicable RERA requirements remain important.

9. Is the Development Agreement now required to be approved by the General Body?

The 2026 Government Order specifically provides for the Development Agreement to be subject to terms and conditions approved by the General Body. The society should therefore not treat the agreement as an unrestricted Managing Committee decision.

10. What is the new timeline for PAAA?

Individual PAAA must be executed within three months after registration of the Development Agreement under the 2026 Government Order.

11. Does Section 91 of the MCS Act cease to apply to redevelopment disputes?

No. The change in wording of the Government Order does not repeal Section 91. The appropriate forum depends on the nature of the dispute, the parties and the applicable statutory provisions.

12. Do the 2026 directions automatically apply to every redevelopment project already underway?

The Government Order does not provide a detailed transitional mechanism for every ongoing project. The legal position should be assessed according to the stage of the project, resolutions already passed, agreements executed, approvals obtained and existing rights.


24. Conclusion: The 2026 Framework Demands Better Documentation and More Informed Decisions

The 30 September 2026 Government Order retains several foundational requirements of the 2019 framework, including the one-fifth requisition threshold, two-thirds quorum, 51% approval requirement, PMC appointment, developer selection procedure and registration of redevelopment agreements.

However, it introduces important changes in how societies are expected to conduct redevelopment.

The most significant developments include:

  • Recognition of eligible virtual participation, subject to physical attendance requirements.
  • More detailed project feasibility reporting.
  • A defined timeline for review of the project report.
  • General Body approval of the tender draft.
  • A longer first tender extension.
  • A defined timeline for appointment of the Registrar’s authorised officer.
  • Express provision for secret ballot in developer selection.
  • More detailed member document-inspection rights.
  • General Body approval of the Development Agreement.
  • General Body discretion regarding the bank guarantee’s proportion and form.
  • A three-month timeline for individual PAAA.
  • A defined post-possession membership process.
  • Express emphasis on accountability for specified violations.

The revised framework places greater importance on informed member participation, proper records and contractual protection.

For housing societies, the key lesson is that redevelopment should not be treated as a transaction in which the developer’s offer alone determines the outcome.

The society must understand its land, development potential, financial requirements and contractual rights before making decisions that may affect members for several years.

A well-documented redevelopment process is not merely a procedural requirement. It is the foundation for protecting the society and its members.


Related Articles in This 13-Part Redevelopment Guide

  1. Part 1: Housing Society Redevelopment in Maharashtra: The Complete Step-by-Step Roadmap
  2. Part 2: 2019 vs 2026 Government Order: What Has Changed in Maharashtra Housing Society Redevelopment?
  3. Part 3: Before You Begin: Legal, Structural and Financial Checks Before Housing Society Redevelopment
  4. Part 4: Special General Body Meeting for Redevelopment: Notice, Quorum, Voting and Legal Requirements
  5. Part 5: Role of Architect and PMC in Housing Society Redevelopment
  6. Part 6: Tender Process for Housing Society Redevelopment: Rules, Transparency and Developer Offers
  7. Part 7: Developer Selection in Housing Society Redevelopment: Registrar’s Authorised Officer and Voting Procedure
  8. Part 8: Developer Due Diligence: How a Housing Society Should Verify a Redeveloper
  9. Part 9: Development Agreement and PAAA: Protecting Members’ Rights in Redevelopment
  10. Part 10: From Demolition to Possession: Construction, Approvals and Handover
  11. Part 11: Self-Redevelopment and Group Redevelopment in Maharashtra
  12. Part 12: Dissenting, Absent, Deceased and NRI Members in Housing Society Redevelopment
  13. Part 13: Housing Society Redevelopment FAQs, Legal Checklist and Glossary
  14. Download Maharashtra Government GR सगृयो-2026/प्र.क्र.108/14-स for Re-Development dated 30/09/2026

About Advocate Ketan Palshikar

Advocate Ketan Palshikar practises in Pune, Maharashtra, with a focus on property documentation, conveyancing, title verification and legal due diligence.

For housing societies and property owners considering redevelopment, proper legal review of title documents, redevelopment resolutions, tender conditions, Development Agreements, Permanent Alternate Accommodation Agreements and related property documentation can help identify risks and protect contractual rights.

For professional assistance relating to property documentation and redevelopment agreements, contact Advocate Ketan Palshikar and Associates, Pune.


Legal Disclaimer

This article is intended for general legal information and educational purposes. It compares the Government of Maharashtra’s Government Resolution dated 4 July 2019 with the Government Order dated 30 September 2026, as understood on 14 November 2026.

The applicability of redevelopment provisions may depend on the society’s legal status, the stage of the redevelopment project, land title, applicable development regulations, existing agreements, court orders and other prevailing laws.

The position concerning ongoing redevelopment projects and the interaction between the Government Order and statutory provisions should be examined on a case-by-case basis.

A housing society should obtain project-specific legal, technical and financial advice before taking redevelopment decisions or executing binding documents.