Part 8 of 13 · Redevelopment Guide for Housing Societies (Pune & PCMC)

By Advocate Ketan Palshikar | Last updated: 15 November 2026 | Based on Government Order No. SGHYO-2026/CR-108/14-S dated 30 September 2026

1. Introduction

Selection of a developer does not mean that the society should immediately proceed with the execution of the Development Agreement without further verification.

A developer may submit an attractive redevelopment proposal offering additional carpet area, corpus fund, transit rent, amenities and other benefits. However, the society must independently examine whether the developer has the legal standing, financial strength, technical capability and professional experience to fulfil those commitments.

Housing society redevelopment involves substantial financial exposure and long-term contractual obligations. Once members vacate their existing premises, they become dependent on the developer’s ability to complete the project and deliver the promised rehabilitation premises.

If the developer lacks adequate financial resources, has a history of incomplete projects, is involved in insolvency proceedings or does not possess the necessary technical capacity, the society and its members may face serious difficulties.

Therefore, developer due diligence should be treated as a separate and essential exercise between developer selection and execution of the Development Agreement.

The purpose is not merely to verify whether the developer is a registered business entity. It is to establish whether the developer is capable of implementing the particular redevelopment project on the terms offered to the society.

2. Legal Position Under the 2026 Government Order

The Government Order dated 30 September 2026 prescribes the procedure for selecting a developer and identifies several important matters that must be incorporated into the Development Agreement.

However, it does not provide a single exhaustive statutory checklist for conducting legal, financial and technical due diligence of the selected developer.

Accordingly, the following distinction should be maintained:

A. Requirements expressly addressed by the Government Order

  • Developer selection through the prescribed Special General Body Meeting.
  • Selection based on experience, quality, financial capacity, technical capacity and competitive offers.
  • Written consent of the selected developer.
  • Execution of the Development Agreement within three months.
  • Bank guarantee in the proportion and form approved by the General Body.
  • Completion period of two years, with an exceptional extension up to three years, calculated as prescribed.
  • Alternative accommodation, rent, deposit or transit accommodation arrangements.
  • Registration of the Development Agreement and individual Permanent Alternate Accommodation Agreements.
  • Clear mention of RERA carpet area.
  • Non-transferability of development rights.
  • Vacating of premises only after all legal approvals and registration of individual PAAAs.
  • Other contractual and member-protection provisions specified in Paragraph 13.

B. Additional due diligence recommended for protection of the society

  • Verification of the developer’s legal constitution and ownership.
  • Examination of directors, partners and authorised signatories.
  • Verification of financial statements and borrowing capacity.
  • Examination of ongoing and completed projects.
  • Verification of MahaRERA registrations and project disclosures, wherever applicable.
  • Search for insolvency, winding-up and material litigation proceedings.
  • Examination of land, development rights and project-specific permissions.
  • Assessment of construction resources and technical team.
  • Verification of funding arrangements and bank guarantee capability.
  • Independent legal review of the proposed Development Agreement.

The additional checks are recommended risk-management measures. They should not be misrepresented as an exhaustive list expressly mandated by the 2026 Government Order.

3. Verification of the Developer’s Legal Identity and Constitution

The first step is to identify the exact legal entity that will enter into the Development Agreement.

A developer may operate as:

  • Proprietorship concern;
  • Partnership firm;
  • Limited Liability Partnership (LLP);
  • Private Limited Company;
  • Public Limited Company; or
  • Another legally recognised business entity.

The society should obtain and examine the relevant constitution documents.

3.1 Proprietorship Concern

Where the developer operates as a proprietorship concern, the society should verify:

  • Proprietor’s full legal name.
  • Identity and address documents.
  • Business registration details, where applicable.
  • GST registration, where applicable.
  • PAN details.
  • Business address.
  • Authority and capacity of the proprietor to execute the Development Agreement.

A proprietorship concern is not a separate legal entity distinct from its proprietor. The agreement and supporting documents should correctly identify the person undertaking the contractual obligations.

3.2 Partnership Firm

Where the developer is a partnership firm, the society should obtain:

  • Partnership deed and amendments.
  • Registration details, where applicable.
  • Firm PAN.
  • GST registration, where applicable.
  • Names and details of all partners.
  • Authority of the partner executing the agreement.
  • Relevant resolution or authorisation of the partners.

The society should examine whether the partnership deed permits the firm to undertake the redevelopment transaction and whether the executing partner has the necessary authority.

3.3 Limited Liability Partnership

Where the developer is an LLP, the society should examine:

  • Certificate of incorporation.
  • LLP Identification Number (LLPIN).
  • LLP Agreement and amendments.
  • Details of designated partners.
  • MCA master data.
  • Authorisation of the designated partner or other authorised person executing the agreement.
  • Relevant resolutions or consents, as applicable.

3.4 Private Limited or Public Limited Company

Where the developer is a company, the society should obtain:

  • Certificate of Incorporation.
  • Corporate Identification Number (CIN).
  • Memorandum of Association.
  • Articles of Association.
  • Current company master data.
  • Details of directors.
  • Shareholding information, where relevant.
  • Board resolution approving the redevelopment transaction.
  • Authorisation in favour of the person executing the agreement.
  • Details of charges registered with the Registrar of Companies.

The society should also verify whether the company’s constitutional documents and corporate approvals permit the proposed transaction.

3.5 Why Is the Exact Legal Entity Important?

A developer may advertise and conduct business under a trade name that differs from the legal name of the entity entering into the agreement.

The society should not rely solely on the developer’s brand name or business card.

The entity selected by the General Body, the entity submitting the tender, the entity executing the Development Agreement and the entity responsible for project implementation should be clearly identified.

If the developer proposes that another group company, subsidiary, associate or special-purpose entity will execute the agreement, the society should obtain independent legal advice before accepting the arrangement.

4. Verification of Directors, Partners and Persons in Control

The society should identify the individuals who control and manage the developer entity.

This is particularly important where the developer operates through a company or LLP.

The examination should include:

  • Names of directors or designated partners.
  • Their roles and responsibilities.
  • Changes in management during recent years.
  • Authorised signatories.
  • Relevant disqualification or regulatory information.
  • Material involvement in previous redevelopment projects.
  • Associations with other development entities.

The society should also identify the persons who will actually supervise and implement the project.

A developer may have a registered office and a corporate structure but may depend entirely on external contractors for construction and project management.

The society should understand who will be responsible for:

  • Project financing.
  • Approvals.
  • Construction.
  • Procurement.
  • Site supervision.
  • Member coordination.
  • Payment of transit rent.
  • Completion and handover.

The contractual obligations should remain clearly enforceable against the selected developer, irrespective of its internal business arrangements.

5. Verification of the Developer’s Past Projects and Track Record

A developer’s previous performance is one of the most useful indicators of its capacity to complete the proposed redevelopment.

The society should obtain a list of completed and ongoing projects.

The information should be independently verified wherever possible.

5.1 Completed Projects

For completed projects, the society should examine:

  • Project name and location.
  • Nature and size of the project.
  • Whether it involved housing society redevelopment.
  • Date of commencement.
  • Date of completion.
  • Occupation Certificate (OC) status.
  • Number of residential and commercial units.
  • Construction quality.
  • Compliance with the original contractual commitments.
  • Whether possession was delivered within the agreed timeline.

The society should not treat a project as completed merely because the developer has substantially finished construction.

The relevant approvals and actual possession status should also be examined.

5.2 Ongoing Projects

For ongoing projects, the society should obtain:

  • Project details and location.
  • Construction stage.
  • Original and revised completion timelines.
  • MahaRERA registration details, where applicable.
  • Details of delays.
  • Reasons for delays.
  • Pending approvals.
  • Funding status.
  • Outstanding obligations to existing customers or members.

A developer undertaking several projects simultaneously may face financial, operational or management constraints.

The society should assess whether the developer has sufficient resources to undertake another project without compromising the existing commitments.

5.3 Redevelopment Experience

Experience in ordinary residential construction is not necessarily equivalent to experience in cooperative housing society redevelopment.

Redevelopment involves additional complexities such as:

  • Coordinating with multiple existing members.
  • Executing individual PAAAs.
  • Arranging transit accommodation or rent.
  • Managing vacation of existing premises.
  • Handling existing possession rights.
  • Obtaining multiple approvals.
  • Meeting rehabilitation obligations.
  • Managing construction while maintaining contractual obligations to the society.

The society should therefore give due weight to actual redevelopment experience.

5.4 References From Previous Societies

Where possible, the society should contact the office bearers or members of other societies redeveloped by the developer.

Useful questions include:

  • Was the project completed within the agreed period?
  • Was the promised carpet area delivered?
  • Were rent and other payments made regularly?
  • Were construction specifications followed?
  • Were there disputes regarding amenities or parking?
  • Were approvals and occupation permissions obtained?
  • Did the developer cooperate with the society?
  • Were there material deviations from the Development Agreement?

Direct feedback from previous societies may reveal issues that are not apparent from marketing material or project brochures.

6. Financial Due Diligence

Financial capacity is one of the most important aspects of developer verification.

A developer may submit a commercially attractive proposal but lack sufficient liquidity to fund construction, pay transit rent, arrange approvals and meet other obligations.

The society should therefore examine both the developer’s financial position and the financial feasibility of the proposed project.

6.1 Audited Financial Statements

Where available and appropriate to the developer’s legal constitution, the society should obtain recent audited financial statements.

These may include:

  • Balance Sheet.
  • Profit and Loss Account.
  • Cash Flow Statement.
  • Auditor’s Report.
  • Notes to Accounts.
  • Details of borrowings.
  • Details of contingent liabilities.
  • Related-party transactions, where material.

The financial statements should be examined by a qualified finance professional.

6.2 Net Worth

The society should examine the developer’s net worth.

Net worth may provide an indication of the developer’s financial strength, but it should not be considered in isolation.

A developer may report substantial assets while having limited available cash or significant existing liabilities.

The nature, ownership, marketability and encumbrances of the reported assets should also be considered.

6.3 Liquidity and Working Capital

Redevelopment requires funds at different stages.

The developer may have to arrange:

  • Transit rent.
  • Security deposits.
  • Brokerage, where contractually agreed.
  • Approval and statutory charges.
  • Professional fees.
  • Construction expenditure.
  • Procurement and labour payments.
  • Bank guarantee margins or collateral.
  • Other project-related expenses.

The society should assess whether the developer has sufficient liquidity to meet these obligations as they arise.

6.4 Existing Borrowings and Financial Commitments

The society should obtain information concerning:

  • Existing bank loans.
  • Secured and unsecured borrowings.
  • Charges over assets.
  • Guarantees issued.
  • Existing project finance obligations.
  • Material overdue liabilities.
  • Pending recovery proceedings, where relevant.

The objective is to identify whether existing commitments may affect the developer’s ability to fund the proposed redevelopment.

6.5 Funding Plan for the Redevelopment Project

The developer should explain how the project will be funded.

Possible sources may include:

  • Internal accruals.
  • Bank finance.
  • Institutional funding.
  • Project finance.
  • Sale proceeds from free-sale components.
  • Other legally permissible sources.

The society should examine whether the proposed funding plan is realistic and whether the developer is dependent on uncertain future receipts to meet immediate rehabilitation obligations.

A project that depends heavily on future sale proceeds may carry greater execution risk if market conditions deteriorate.

6.6 Ability to Pay Transit Rent

Transit rent is a recurring financial obligation.

The developer may have to pay rent for a substantial period before the redevelopment project generates sufficient sale proceeds.

The society should therefore assess whether the developer can meet these payments even in the event of construction delays or slower sales.

The developer’s financial capacity should be considered in relation to the number of existing members, proposed rent, deposit, escalation and expected construction period.

7. Insolvency, Bankruptcy and Material Litigation Search

The society should conduct appropriate searches to identify material legal or financial proceedings involving the developer.

These checks are particularly important because insolvency or serious litigation may affect the developer’s ability to perform its contractual obligations.

7.1 Insolvency Proceedings

The society should examine whether the developer or relevant group entity is subject to:

  • Corporate insolvency resolution proceedings.
  • Liquidation proceedings.
  • Winding-up proceedings.
  • Material insolvency applications.
  • Other significant proceedings affecting its assets or operations.

For corporate developers, relevant information may be available through official insolvency records and other public sources.

7.2 Litigation Search

The society should seek disclosure of material litigation involving:

  • Existing redevelopment projects.
  • Construction contracts.
  • Non-payment of contractors.
  • Delayed possession.
  • Consumer complaints.
  • Real estate regulatory proceedings.
  • Land title disputes.
  • Financial defaults.
  • Criminal proceedings involving alleged fraud or financial misconduct, where relevant.

The existence of litigation does not automatically disqualify a developer.

The nature, stage, financial exposure and possible effect on project execution should be examined.

7.3 Developer’s Written Disclosure

The society should obtain a written declaration from the developer disclosing material litigation, insolvency proceedings, financial defaults and regulatory actions.

The declaration should be appropriately drafted and supported by documentary information.

A mere declaration should not replace independent verification.

8. MahaRERA Verification

Where the proposed project or the developer’s relevant projects fall within the scope of the Real Estate (Regulation and Development) Act, 2016, the society should examine the relevant MahaRERA records.

The society should verify:

  • Project registration number.
  • Promoter’s legal name.
  • Project location.
  • Registration validity.
  • Declared completion date.
  • Extensions, if any.
  • Quarterly project updates, where applicable.
  • Disclosed approvals.
  • Project progress.
  • Complaints and orders.
  • Details of the promoter’s other registered projects.

8.1 Check the Promoter, Not Merely the Brand Name

The society should verify the legal entity identified as the promoter in the relevant MahaRERA records.

A developer group may have multiple companies or project-specific entities.

The society should not assume that a favourable MahaRERA record of one group company establishes the performance or financial capacity of another entity.

8.2 MahaRERA Registration Is Not a Guarantee of Performance

Registration under RERA should not be treated as a guarantee that the developer will complete the redevelopment project successfully.

It is one important verification point among several.

The society should examine the actual project disclosures, progress, compliance history and relevant orders.

8.3 Is Every Society Redevelopment Project Required to Be Registered With MahaRERA?

Not necessarily.

Section 3 of the RERA Act contains the statutory framework governing registration and specified exemptions.

In particular, the exemption concerning renovation, repair or redevelopment without marketing, advertising, selling or new allotment must be considered on its own terms.

A redevelopment project involving a sale component or new allotments may require a different analysis.

The society should obtain project-specific legal advice rather than assume that all redevelopment projects are automatically exempt or automatically registrable.

9. Verification of Technical and Construction Capacity

The developer must have the ability to execute the proposed construction in accordance with the approved plans and contractual specifications.

The society should examine the developer’s technical resources.

9.1 Construction Team

The developer should provide details of:

  • Project architect.
  • Structural consultant.
  • Civil engineering team.
  • Site engineers.
  • Project manager.
  • Contractors.
  • Quality-control personnel.
  • Safety personnel.
  • Other relevant technical professionals.

The society should examine whether the proposed team has adequate experience and capacity.

9.2 Construction Equipment and Resources

Depending on the project’s size, the society may examine:

  • Construction equipment.
  • Labour arrangements.
  • Procurement capacity.
  • Site-management arrangements.
  • Construction methodology.
  • Quality-control systems.
  • Safety systems.

The developer need not necessarily own every resource. However, it should demonstrate that the resources required for implementation are reliably available.

9.3 Construction Quality

The society should examine the developer’s previous construction quality through:

  • Site visits to completed projects.
  • Inspection of available specifications.
  • Feedback from previous societies or customers.
  • Information concerning structural or quality-related complaints.
  • Details of rectification or warranty obligations.

The society should avoid relying solely on brochures, sample flats or promotional presentations.

10. Project-Specific Feasibility and Funding Assessment

Apart from examining the developer’s general financial position, the society should assess the financial feasibility of the particular redevelopment project.

A developer may be financially strong but still submit an unrealistic proposal for a particular property.

The society’s Architect / PMC and financial consultant should examine:

  • Estimated construction cost.
  • Approval and statutory charges.
  • Transit rent and deposits.
  • Rehabilitation area.
  • Free-sale component.
  • Expected saleable inventory.
  • Indicative sale values.
  • Finance costs.
  • Project duration.
  • Contingency provisions.
  • Funding requirements at different stages.

The objective is to determine whether the developer’s offer is commercially sustainable.

For example, a developer may offer exceptionally high additional carpet area and corpus fund. However, if the available free-sale component and expected project revenue do not support the proposed commitments, the offer may be commercially unrealistic.

The society should not evaluate offers solely on the basis of the benefits promised to members.

11. Verification of the Proposed Bank Guarantee

The 2026 Government Order specifically provides that the General Body must decide the proportion and form of the bank guarantee to be furnished by the developer.

This is an important financial safeguard.

The society should not treat the developer’s statement that it will provide a bank guarantee at a later stage as sufficient.

The proposed guarantee should be examined before execution of the Development Agreement.

The following matters should be considered:

  • Name and credibility of the issuing bank.
  • Identity of the beneficiary.
  • Guaranteed amount.
  • Validity period.
  • Renewal requirements.
  • Conditions for invocation.
  • Whether the guarantee is unconditional and payable on demand, if so approved and legally appropriate.
  • Whether the guarantee covers the relevant obligations.
  • Procedure for extension or replacement.
  • Consequences of failure to renew.

The society should obtain independent legal and financial advice regarding the wording and enforceability of the bank guarantee.

A bank guarantee is useful only if its terms permit effective enforcement when the contractual conditions for invocation are satisfied.

12. Examination of the Developer’s Proposed Project Structure

The society should understand the exact structure through which the developer proposes to implement the redevelopment.

For example:

  • Will the selected developer execute the project directly?
  • Will a separate project company be created?
  • Will construction be undertaken through a related entity?
  • Will the developer appoint a principal contractor?
  • Will project finance be obtained from a bank or financial institution?
  • Will any third party be granted rights over the project?

The society should distinguish between ordinary outsourcing of construction work and transfer of the development rights or contractual obligations.

The 2026 Government Order specifically provides that development rights granted to the developer are non-transferable.

The society should therefore ensure that the Development Agreement does not permit the developer to transfer or assign the development rights contrary to this requirement.

Any proposed arrangement involving group entities, contractors, lenders or other third parties should be examined carefully to ensure that the selected developer remains contractually responsible for performance.

13. Conflict of Interest and Related-Party Connections

The society should examine whether the developer has any undisclosed relationship with:

  • Managing Committee members.
  • Office bearers.
  • Members involved in the redevelopment process.
  • Architect / PMC.
  • Other consultants.
  • Contractors.
  • Persons influencing the tender process.

The 2026 Government Order expressly provides that no Managing Committee member or office bearer of the society, or their relative, should be the developer.

The society should examine this restriction carefully and obtain appropriate declarations.

In addition, any other actual or potential conflict of interest should be disclosed and addressed.

The purpose is to ensure that the developer-selection process and subsequent contractual arrangements are not influenced by undisclosed personal or financial interests.

14. Developer Due Diligence Report

The society should not rely on informal discussions or scattered documents.

A consolidated Developer Due Diligence Report should be prepared before execution of the Development Agreement.

The report may be divided into the following sections:

A. Legal Identity and Constitution

  • Legal name and entity type.
  • Incorporation or registration details.
  • Constitution documents.
  • Directors, partners or proprietor.
  • Authorised signatories.
  • Corporate approvals.
  • Related entities.

B. Past Performance

  • Completed projects.
  • Ongoing projects.
  • Redevelopment experience.
  • Occupation Certificates.
  • Project delays.
  • Member complaints.
  • References from previous societies.

C. Financial Position

  • Audited financial statements.
  • Net worth.
  • Liquidity.
  • Working capital.
  • Borrowings.
  • Existing financial commitments.
  • Funding arrangements.
  • Ability to pay transit rent.

D. Litigation and Regulatory Position

  • Insolvency proceedings.
  • Material civil litigation.
  • Criminal proceedings involving relevant allegations.
  • MahaRERA records.
  • Regulatory orders.
  • Material defaults.

E. Technical Capacity

  • Technical team.
  • Architects and consultants.
  • Construction resources.
  • Quality-control systems.
  • Safety systems.
  • Project management arrangements.

F. Project-Specific Assessment

  • Financial feasibility.
  • Project funding.
  • Construction cost.
  • Rehabilitation obligations.
  • Free-sale component.
  • Approval requirements.
  • Bank guarantee.
  • Implementation schedule.

G. Final Assessment

The report should identify:

  • Material risks.
  • Missing documents.
  • Unresolved issues.
  • Conditions requiring clarification.
  • Contractual safeguards recommended.
  • Whether the developer appears capable of undertaking the project on the offered terms.

The report should be placed before the appropriate society authorities and preserved in the redevelopment records.

15. What If Due Diligence Reveals Serious Problems?

Due diligence may reveal material concerns after the developer has been selected.

Examples include:

  • Incorrect financial disclosures.
  • Serious undisclosed litigation.
  • Insolvency proceedings.
  • Lack of funding.
  • Unverifiable project experience.
  • Material deviations from the tender.
  • Undisclosed related-party arrangements.
  • Inability to provide the approved bank guarantee.
  • Inconsistency between the tendering entity and the proposed contracting entity.

The society should not ignore such findings merely because the developer has already been selected.

However, the Managing Committee should also avoid unilaterally cancelling the selection or entering into a fresh arrangement without examining the applicable procedure.

The appropriate course should be determined after considering:

  1. The nature and seriousness of the issue.
  2. The tender conditions.
  3. The General Body resolution.
  4. The selected developer’s written consent.
  5. The applicable provisions of the 2026 Government Order.
  6. The legal consequences of withdrawal or cancellation.
  7. Whether further General Body approval or other procedural steps are required.

Independent legal advice should be obtained before taking action that may affect the developer-selection decision.

16. Due Diligence Must Be Completed Before Execution of the Development Agreement

The 2026 Government Order requires the Managing Committee to execute the Development Agreement with the developer within three months, subject to the conditions approved by the General Body and with the guidance of the Architect / PMC.

The prescribed timeline should be respected.

However, the society should not treat the three-month period as a reason to execute an inadequately examined agreement.

The due diligence exercise should be organised promptly after developer selection so that the society can complete the necessary verification and contractual negotiations within the prescribed period.

The Development Agreement should accurately reflect the developer’s approved offer and incorporate the safeguards required under the Government Order.

17. Practical Checklist: Developer Due Diligence

The following checklist may be used by the Managing Committee and its professional advisers.

Legal and Corporate Verification

  • Exact legal identity of the selected developer verified.
  • Constitution documents obtained.
  • Registration or incorporation details verified.
  • Directors, partners or proprietor identified.
  • Authorised signatory verified.
  • Relevant corporate or partnership authorisations obtained.
  • Related entities and proposed project structure examined.
  • Conflict-of-interest disclosures obtained.

Track Record

  • List of completed projects obtained.
  • List of ongoing projects obtained.
  • Redevelopment experience verified.
  • Completion and OC status examined.
  • Previous society references obtained.
  • Material delays and defaults examined.
  • Construction quality assessed.

Financial Verification

  • Recent audited financial statements obtained.
  • Net worth examined.
  • Liquidity and working capital assessed.
  • Borrowings and liabilities examined.
  • Existing project commitments reviewed.
  • Project funding plan obtained.
  • Transit rent payment capacity assessed.
  • Bank guarantee capability examined.

Legal and Regulatory Verification

  • Insolvency and winding-up searches conducted, as relevant.
  • Material litigation disclosed and examined.
  • MahaRERA records checked, where applicable.
  • Regulatory orders and complaints examined.
  • Material defaults and enforcement proceedings reviewed.

Technical Verification

  • Project architect and technical team identified.
  • Construction resources assessed.
  • Contractor arrangements examined.
  • Quality-control systems reviewed.
  • Safety arrangements examined.
  • Project management capability assessed.

Project-Specific Assessment

  • Financial feasibility independently examined.
  • Development potential and assumptions reviewed.
  • Rehabilitation commitments verified.
  • Transit accommodation arrangements examined.
  • Bank guarantee terms reviewed.
  • Construction schedule assessed.
  • Material tender deviations identified.
  • Development Agreement draft legally vetted.

18. Frequently Asked Questions

Q1. Is developer due diligence expressly prescribed as a separate stage under the 2026 Government Order?

The Government Order prescribes developer selection based on relevant criteria such as experience, quality, financial capacity and technical capacity. It also specifies contractual safeguards. It does not provide a separate exhaustive due diligence checklist. Independent verification is recommended to protect the society before execution of the Development Agreement.

Q2. Is a developer required to have completed previous redevelopment projects?

The society should examine the developer’s experience and track record. The Government Order identifies experience as a relevant consideration for selection. The precise eligibility conditions should also be read with the approved tender document.

Q3. Is a high net worth sufficient to establish financial capability?

No. Net worth is only one indicator. Liquidity, borrowings, working capital, existing commitments and project-specific funding must also be examined.

Q4. Should the society check the developer’s MahaRERA record?

Yes, wherever relevant. The society should examine applicable project registrations, disclosures, progress, complaints and orders. However, RERA registration alone does not guarantee successful completion.

Q5. Can a developer transfer the redevelopment project to another company?

The 2026 Government Order expressly provides that development rights granted to the developer are non-transferable. Any proposed corporate or contractual arrangement must be examined carefully so that it does not defeat this requirement.

Q6. Is a bank guarantee compulsory?

The 2026 Government Order requires the General Body to decide the proportion and form of the bank guarantee to be provided by the developer. The society should ensure that the approved arrangement is properly incorporated into the Development Agreement.

Q7. Can the society conduct due diligence after execution of the Development Agreement?

The society should complete material due diligence before execution. Post-execution verification may be useful for continuing monitoring, but it should not replace the examination required before entering into the contract.

Q8. What if the selected developer is unable to provide the approved bank guarantee?

The society should examine the tender conditions, selection resolution and proposed contractual terms. It should obtain legal advice before deciding whether to grant time, enforce the approved terms or take further action.

Q9. Can the Managing Committee independently replace the selected developer if due diligence reveals serious concerns?

The Managing Committee should not assume that it has unrestricted authority to replace a developer selected through the prescribed General Body process. The legal and procedural consequences must be examined, and any further decision should follow the applicable requirements.

Q10. Who should conduct developer due diligence?

The society should involve an advocate for legal and corporate verification, a qualified finance professional for financial assessment, and the appointed Architect / PMC for technical and project-related examination. The responsibilities should be clearly allocated.

19. Conclusion

Developer selection is only one stage in the redevelopment process. The society must independently establish whether the selected developer is genuinely capable of fulfilling the commitments made in the tender.

Legal identity, financial strength, construction capacity, past performance, litigation history, project funding and bank guarantee capability are all important considerations.

A developer’s commercial offer should never be evaluated in isolation from its ability to perform.

The society should complete a structured due diligence exercise, document its findings and address material risks through appropriate contractual safeguards.

A properly selected and independently verified developer provides the foundation for a secure Development Agreement. The next stage is to convert the approved redevelopment proposal into a comprehensive, enforceable and properly registered contract.


Related Articles in This 13-Part Redevelopment Guide

  1. Part 1: Housing Society Redevelopment in Maharashtra: The Complete Step-by-Step Roadmap
  2. Part 2: 2019 vs 2026 Government Order: What Has Changed in Maharashtra Housing Society Redevelopment?
  3. Part 3: Before You Begin: Legal, Structural and Financial Checks Before Housing Society Redevelopment
  4. Part 4: Special General Body Meeting for Redevelopment: Notice, Quorum, Voting and Legal Requirements
  5. Part 5: Role of Architect and PMC in Housing Society Redevelopment
  6. Part 6: Tender Process for Housing Society Redevelopment: Rules, Transparency and Developer Offers
  7. Part 7: Developer Selection in Housing Society Redevelopment: Registrar’s Authorised Officer and Voting Procedure
  8. Part 8: Developer Due Diligence: How a Housing Society Should Verify a Redeveloper
  9. Part 9: Development Agreement and PAAA: Protecting Members’ Rights in Redevelopment
  10. Part 10: From Demolition to Possession: Construction, Approvals and Handover
  11. Part 11: Self-Redevelopment and Group Redevelopment in Maharashtra
  12. Part 12: Dissenting, Absent, Deceased and NRI Members in Housing Society Redevelopment
  13. Part 13: Housing Society Redevelopment FAQs, Legal Checklist and Glossary
  14. Download Maharashtra Government GR सगृयो-2026/प्र.क्र.108/14-स for Re-Development dated 30/09/2026

Legal Disclaimer

This article is intended for general legal information and educational purposes. It is based on the Maharashtra Government Order dated 30 September 2026, read with the relevant legal and regulatory framework. The due diligence checks described in this article include recommended risk-management measures and should not all be understood as express requirements of the Government Order. The scope of verification will depend on the developer’s legal constitution, the nature of the project and the applicable laws. Societies should obtain appropriate legal, financial and technical advice before executing redevelopment agreements.