Part 1 of 13 · Redevelopment Guide for Housing Societies (Pune & PCMC)
By Advocate Ketan Palshikar | Last updated: 14 November 2026 | Based on Government Order No. SGHYO-2026/CR-108/14-S dated 30 September 2026
Introduction: Understanding Housing Society Redevelopment
Redevelopment of a cooperative housing society is not merely a construction project. It is a complex legal, financial, technical and administrative exercise involving the society, its members, architects, project management consultants, developers, financial institutions and planning authorities.
For members, redevelopment may provide a new apartment, additional carpet area, modern amenities, improved infrastructure and a safer building. For the society, it may offer an opportunity to make better use of its land and resolve long-standing structural or maintenance concerns.
However, redevelopment also involves substantial risks. An improperly conducted process, inadequate due diligence, an unsuitable developer, weak contractual safeguards or incomplete documentation can expose the society and its members to prolonged delays, financial losses and legal disputes.
The redevelopment process must therefore be approached systematically, with transparency, proper documentation and compliance with the applicable legal framework at every stage.
In Maharashtra, the principal procedural framework is now governed by the Government Order dated 30 September 2026, issued under Section 79A of the Maharashtra Co-operative Societies Act, 1960. The order supersedes the earlier Government Resolution dated 4 July 2019 and the circulars issued under it. Accordingly, societies undertaking redevelopment must refer to the revised 2026 directions rather than mechanically following the earlier procedure.
This guide explains the redevelopment process from the preliminary assessment of a building to developer selection, execution of agreements, construction and eventual possession.
It is intended for cooperative housing societies, managing committee members, individual flat owners, senior citizens, property owners and other stakeholders considering redevelopment in Pune and the surrounding region.
1. The Legal Framework Governing Redevelopment in Maharashtra
Before initiating redevelopment, a society must understand that no single statute or Government Order governs every aspect of the project.
The legal framework consists of several laws and regulatory instruments operating together.
1.1 Maharashtra Co-operative Societies Act, 1960
The Maharashtra Co-operative Societies Act, 1960 (MCS Act) governs the legal constitution, administration and functioning of cooperative housing societies.
Some of its important provisions in the context of redevelopment include:
- Section 72: Recognises the general body as the final authority of the society, subject to the Act, Rules and applicable bye-laws.
- Section 73: Deals with the management of the society through its managing committee.
- Section 76: Provides for convening a special general meeting, including on a requisition by the prescribed number of members.
- Section 79A: Empowers the State Government to issue directions to cooperative societies in the public interest.
- Sections 78A and 79A(3): May become relevant where statutory conditions for action against responsible committee members or office bearers are satisfied.
The Act and Rules govern the society’s internal decision-making, membership, voting, committee functioning and other statutory matters.
1.2 Maharashtra Co-operative Societies Rules, 1961
The Maharashtra Co-operative Societies Rules, 1961 supplement the Act and prescribe the procedural framework for the functioning of cooperative societies.
The 2026 amendments to the Rules, including the provisions relating to cooperative housing societies, must also be considered while conducting redevelopment-related meetings and society business.
The applicable Rules and the 30 September 2026 Government Order should be read together. A society should not assume that compliance with one document automatically satisfies every requirement under the other.
1.3 Government Order dated 30 September 2026
The Government of Maharashtra issued Government Order No. SGHYO-2026/CR-108/14-S dated 30 September 2026 under Section 79A of the MCS Act.
It establishes a detailed procedural framework for redevelopment, including:
- Preliminary redevelopment decision.
- Convening of a Special General Body Meeting.
- Selection and appointment of an Architect / Project Management Consultant (PMC).
- Preparation and approval of the project report.
- Preparation and publication of tender documents.
- Invitation and scrutiny of tenders.
- Selection of the developer.
- Execution of the Development Agreement.
- Execution of individual Permanent Alternate Accommodation Agreements.
- Construction, possession and other member-protection requirements.
The order applies to developer-led redevelopment, self-redevelopment and group redevelopment. It also provides that the prescribed developer-selection procedure applies, with necessary adaptation, to the appointment of a contractor in self-redevelopment.
1.4 Development Control Regulations and UDCPR
The development potential of a property is governed by the applicable Development Plan and Development Control Regulations, including the Unified Development Control and Promotion Regulations (UDCPR), wherever applicable.
These regulations determine matters such as:
- Permissible Floor Space Index (FSI).
- Premium FSI and other permissible development potential.
- Transferable Development Rights (TDR).
- Incentive FSI, where applicable.
- Setbacks and marginal open spaces.
- Parking requirements.
- Fire access and safety requirements.
- Open spaces and other planning conditions.
The applicable regulations depend on the precise location and planning authority having jurisdiction over the property.
For example, a property within the Pune Municipal Corporation limits may be governed by a different planning framework or specific local provisions from a property falling within the jurisdiction of PCMC, PMRDA or another special planning authority.
A society should therefore obtain a property-specific development feasibility assessment rather than relying on general FSI figures circulated by developers or consultants.
1.5 Real Estate (Regulation and Development) Act, 2016
The Real Estate (Regulation and Development) Act, 2016 (RERA) and the applicable MahaRERA regulations are relevant to redevelopment projects, particularly where the developer proposes to sell newly constructed premises to third-party purchasers.
A redevelopment project is not automatically exempt from RERA merely because existing members are being rehabilitated.
The applicability of registration must be examined in light of the project’s structure, sale component, proposed marketing and allotment, and the statutory exemptions.
1.6 Registration Act, 1908 and Maharashtra Stamp Act
The Development Agreement, individual Permanent Alternate Accommodation Agreements (PAAA), Powers of Attorney and other transaction documents must be examined under the applicable stamp duty and registration laws.
A society should not treat the execution of an agreement as a mere formality. The nature of the rights created, the property involved, the parties and the applicable statutory provisions determine the appropriate documentation, stamp duty and registration requirements.
2. Is Every Old Housing Society Eligible for Redevelopment?
No. The age of a building, by itself, does not automatically establish eligibility under the 30 September 2026 Government Order.
The first paragraph of the Government Order contemplates redevelopment where:
- The competent authority has declared the society’s building to be dilapidated, in a dangerous condition, unsafe for occupation or dangerous to adjoining structures or locations; and
- The society’s building is eligible for redevelopment under the applicable Development Control Regulations.
Both the condition of the building and the applicable planning regulations must therefore be examined.
2.1 Structural Condition of the Building
A society should obtain an appropriate structural assessment from a qualified professional.
Depending on the condition of the building and the applicable local requirements, the society may need to examine:
- Structural audit reports.
- Structural stability certificates.
- Reports identifying structural defects.
- Recommendations for repairs, strengthening or reconstruction.
- Notices or directions issued by the competent authority.
- Any official declaration concerning the building’s dangerous or dilapidated condition.
A structural audit report and a declaration by the competent authority are not necessarily interchangeable. The legal significance of each document must be assessed according to the applicable statutory and local requirements.
2.2 Development Eligibility
Even where a building is old or structurally unsafe, the society must establish whether redevelopment is permissible under the applicable planning regulations.
The relevant assessment may include:
- Land area and plot configuration.
- Existing sanctioned construction.
- Existing authorised built-up area.
- Available FSI and TDR.
- Applicable redevelopment provisions.
- Road width and access.
- Reservations and road widening.
- Open space, margins and parking requirements.
- Special restrictions applicable to the land.
The feasibility report should also identify any additional permissions or restrictions arising from the ownership or tenure of the land.
Important: A developer’s preliminary statement that a society can receive a particular additional carpet area is not a substitute for a proper development feasibility report.
3. The Complete Redevelopment Process at a Glance
Redevelopment should be treated as a sequence of legally connected stages. Each stage should be completed with proper records before the society proceeds to the next stage.
The following table provides an overview of the principal process under the 30 September 2026 Government Order.
| Stage | Principal activity | Key responsibility |
|---|---|---|
| 1 | Preliminary assessment and eligibility | Society and its professional advisers |
| 2 | Requisition for Special General Body Meeting | Members and Managing Committee |
| 3 | Initial redevelopment decision | Special General Body |
| 4 | Selection of Architect / PMC | Special General Body |
| 5 | Project survey and feasibility report | Architect / PMC |
| 6 | Review and approval of project report | Managing Committee and General Body |
| 7 | Tender preparation and publication | Society with professional assistance |
| 8 | Receipt and scrutiny of tenders | Society and PMC |
| 9 | Developer selection | Special General Body in the prescribed presence of the Registrar’s authorised officer |
| 10 | Developer due diligence and final documentation | Society, legal adviser and PMC |
| 11 | Development Agreement and individual PAAA | Society, developer and individual members |
| 12 | Approvals, vacating and commencement | Developer and society |
| 13 | Construction, completion and possession | Developer, society and members |
The process is not simply a matter of obtaining a majority vote and appointing a developer. The society must maintain a proper documentary trail throughout the project.
4. Stage One: Preliminary Assessment Before Initiating Redevelopment
The society should not begin by inviting developers to make informal offers.
The first step should be an objective assessment of the society’s legal, technical and financial position.
4.1 Verify the Society’s Legal Status
The society should examine:
- Registration Certificate.
- Registered bye-laws and amendments.
- Current membership register.
- Share certificates.
- Managing Committee election records.
- Details of the current office bearers.
- Previous General Body and Managing Committee resolutions.
- Audit reports and financial statements.
- Pending statutory or administrative issues.
The society must ensure that the Managing Committee is duly elected and legally constituted in accordance with the applicable law.
The 2026 Government Order specifically states that the redevelopment decision is to be taken by a duly elected and legally constituted Managing Committee. It cannot be taken by a Registrar-appointed authorised officer, administrator or authorised committee merely acting in place of the elected committee.
4.2 Verify Land Ownership and Conveyance
The society should examine the documents establishing its rights over the land and building.
Relevant documents may include:
- Original land conveyance deed.
- Development Agreement.
- Lease deed, where applicable.
- Deemed Conveyance Order and registered conveyance document, where applicable.
- Property Card or 7/12 extract, as relevant.
- City Survey records.
- Sanctioned layout and building plans.
- Property tax records.
- Records of mortgages, charges or encumbrances.
- Relevant permissions issued by the original landowner or planning authority.
The status of conveyance is an important part of the feasibility assessment. The PMC is expected to examine the society’s land and conveyance position while preparing the project report.
However, the absence of a conveyance deed should not automatically be described as an absolute statutory bar to every redevelopment proposal. Its legal and practical consequences depend on the land title, development structure, original documents and the permissions required for the particular project.
4.3 Examine the Physical and Technical Condition
The society should obtain or review:
- Structural audit reports.
- Building plans.
- Actual site measurements.
- Existing carpet and built-up area records.
- Common area details.
- Parking arrangements.
- Building services and infrastructure.
- Existing encroachments or unauthorised alterations, if any.
This information will assist the PMC in preparing a realistic project report.
4.4 Obtain an Initial Legal and Development Feasibility Review
Before committing to any developer’s proposal, the society should understand:
- Whether redevelopment is permissible.
- What development potential may be available.
- Whether the land has title or tenure-related restrictions.
- Whether additional approvals are likely to be necessary.
- Whether the proposed rehabilitation and sale components appear financially viable.
A preliminary review is not the final project report. It is an important safeguard against proceeding on assumptions that later prove incorrect.
5. Stage Two: Requisition and Convening of the Special General Body Meeting
The first formal stage under the 2026 Government Order is the convening of a Special General Body Meeting (SGM) to consider redevelopment.
5.1 Who Can Requisition the Meeting?
At least one-fifth of the society’s members may submit a written application to the Secretary of the duly elected and legally constituted Managing Committee, requesting a Special General Body Meeting to consider redevelopment.
The requisition should be properly documented.
It should ideally include:
- Names and membership details of the requisitioning members.
- Their flat numbers and share certificate details.
- A clear request to convene an SGM.
- The proposed subject of redevelopment.
- Suggestions or preliminary proposals, if any.
- Signatures and date.
The society should preserve proof of submission and receipt.
5.2 Time for Convening the Meeting
The 2026 Government Order provides that:
- The Managing Committee should take note of the requisition within eight days of its receipt.
- The Secretary should convene the Special General Body Meeting within two months.
- The notice and agenda should be served on every member at least 14 days in advance.
- Proof of service should be maintained in the society’s records.
A statutory timing issue must also be considered: Section 76 of the MCS Act contains a separate one-month requirement in relation to a qualifying requisition for a special general meeting. The two-month period mentioned in the 2026 Government Order should not be used as a reason to disregard the statutory provision. The society should obtain legal advice and follow the shorter statutory timeline where applicable.
This is an important example of why the Government Order must be read together with the parent Act and Rules.
5.3 Quotations for Architect / PMC
Before convening the initial SGM, the Managing Committee must obtain quotations from at least three eligible architects / project management consultants for preparing the redevelopment project report.
The Government Order specifies that the relevant architects should be registered with the Council of Architecture under the Architects Act, 1972, and the PMC should meet the prescribed government / local authority panel requirements.
The SGM will select one of the proposed experts.
The society should ensure that the quotations clearly identify:
- Scope of work.
- Professional fees.
- Deliverables.
- Time schedule.
- Experience and qualifications.
- Responsibilities.
- Reporting obligations.
- Conflict-of-interest disclosures.
The objective is to select an independent and competent professional who can evaluate the project in the society’s interest.
5.4 Members’ Suggestions Before the Meeting
Members may submit written suggestions, recommendations and objections relating to redevelopment at least eight days before the meeting.
The Managing Committee should maintain a record of the suggestions received and place them before the meeting.
This is important because redevelopment decisions should be based on informed member participation rather than informal discussions or representations made by individual developers.
6. Stage Three: The Initial Redevelopment Decision
The first SGM must consider whether the society should proceed with redevelopment and the appointment of the professional consultant.
6.1 Quorum
The 2026 Government Order prescribes a quorum of two-thirds of the total membership.
If the quorum is not achieved:
- The meeting must be adjourned.
- The adjourned meeting must be convened within the following month after giving seven days’ notice.
- If the quorum is again not achieved, the meeting is to be cancelled.
- The redevelopment proposal cannot be placed again for approval for three months.
The society should calculate the quorum using its legally valid total membership figure.
6.2 Approval of at Least 51% of Total Membership
The preliminary redevelopment decision requires approval from at least 51% of the society’s total membership.
This requirement must not be confused with 51% of only the members present at the meeting.
For example:
If a society has 100 members:
- Two-thirds quorum requires 67 members, after rounding up.
- At least 51 members must support the redevelopment decision.
- The required support is calculated with reference to the total membership, not merely the number of members attending.
The Government Order also provides for virtual participation in specified circumstances, including members residing abroad, serious illness, disability or other unavoidable reasons. However, it requires at least 51% of the total membership to be physically present at the meeting.
The society should therefore maintain separate and accurate records of physical attendance, eligible virtual attendance and votes cast.
6.3 Recording Opinions and Objections
The minutes should record:
- Members present.
- Members participating virtually.
- Members supporting the proposal.
- Members opposing the proposal.
- Suggestions and objections.
- The name of the member making each recorded representation.
- The resolutions passed.
The Government Order states that opinions, consents or views of absent members are not to be treated as part of the meeting’s decision-making process merely because they are submitted in writing or through other means.
6.4 Written Consent of Members Supporting the Resolution
After the preliminary redevelopment resolution is passed, the Managing Committee must obtain written consent from the members who voted in favour of the resolution before proceeding with further redevelopment steps.
This written consent is distinct from the voting record and should be preserved separately.
Important: The initial redevelopment resolution should not be confused with the later developer-selection resolution. They are separate stages and have separate procedural requirements.
7. Stage Four: Appointment of Architect / Project Management Consultant
Once the initial redevelopment decision is passed, the society must formally appoint the Architect / PMC selected by the SGM.
The Secretary must issue the appointment letter within 30 days of the meeting.
The society must also enter into a written agreement with the appointed professional, incorporating the terms and conditions approved by the General Body.
7.1 Scope of Work of the PMC
The PMC’s initial responsibilities include:
A. Site and Building Survey
- Survey of the existing building.
- Survey of the land.
- Verification of site dimensions.
- Assessment of existing construction.
B. Conveyance and Land Ownership Review
- Examination of conveyance status.
- Review of land ownership documents.
- Identification of title-related issues requiring further action.
C. Development Potential
- Identification of the applicable planning authority.
- Examination of the applicable development regulations.
- Assessment of available FSI and TDR.
- Consideration of applicable redevelopment schemes and benefits.
D. Preparation of a Realistic Project Report
The project report should consider:
- Residential area.
- Commercial area, where applicable.
- Open spaces.
- Garden and recreational areas.
- Parking.
- Construction specifications.
- Member requirements.
- Project feasibility.
- Alternative redevelopment schemes.
Where different development schemes or regulatory options are available, the PMC should prepare separate reports and a comparative statement.
7.2 Timeline for the Project Report
The PMC is required to submit the project report to the Managing Committee within two months from the date of appointment.
The society should ensure that the report is sufficiently detailed to permit members to compare the available options and understand the proposed benefits and limitations.
A report that merely states the additional carpet area or corpus offered by a developer will not adequately serve this purpose.
8. Stage Five: Review and Approval of the Project Report
After receiving the project report, the Secretary must convene a Managing Committee meeting within 30 days.
The PMC should be invited to explain the report and address relevant queries.
8.1 Inspection by Members
The project report must be made available to members for inspection.
The society should communicate the availability of the report and provide members an opportunity to examine it and submit comments.
The Government Order contemplates that members’ comments should be invited at least seven days before the relevant Managing Committee meeting.
8.2 Preparation of Tender Documents
After considering the project report and members’ suggestions, the Managing Committee should proceed with preparation of the tender documents.
One important commercial principle is that the society should determine which of the following will remain constant for comparison:
- Additional carpet area offered to existing members; or
- Corpus fund offered by the developer.
The other commercial terms can then be evaluated along with the technical and financial conditions.
The tender should not be structured in a manner that encourages developers to make unrealistic promises simply to secure selection.
8.3 Approval of Tender Conditions
The draft tender document must be placed before the General Body for approval.
The tender should specify the society’s requirements, including:
- Existing members’ rehabilitation entitlement.
- Proposed additional area, if any.
- Corpus and other financial benefits.
- Rent and transit accommodation.
- Deposit and shifting charges.
- Construction specifications.
- Project completion period.
- Bank guarantee and other security.
- Required approvals.
- Developer’s technical and financial qualifications.
- Consequences of delay or default.
- Proposed contractual safeguards.
The tender should be prepared with professional assistance and should be consistent with the project report and the society’s approved objectives.
9. Stage Six: Invitation and Scrutiny of Tenders
After the General Body approves the tender document, the society must invite tenders in accordance with the 2026 Government Order.
The order requires publication of advertisements in Marathi and English newspapers having the highest circulation in the relevant local area.
The society may also invite experienced developers to participate in the tender process.
9.1 Minimum Number of Tenders
The Government Order provides for a minimum of three tenders.
If fewer than three tenders are received:
- The first extension must be for at least 15 days.
- If the required number is still not received, a second extension of one week is provided.
- If fewer than three tenders are received even after the extensions, the available tenders may be placed before the General Body for consideration.
9.2 Comparative Statement
The PMC should scrutinise the tenders and prepare a comparative statement.
The comparison should not be limited to the additional carpet area or corpus.
It should consider:
- Financial offer.
- Developer’s financial capacity.
- Construction experience.
- Completed projects.
- Ongoing projects.
- Technical capabilities.
- Proposed construction specifications.
- Project timelines.
- Transit accommodation arrangements.
- Bank guarantee.
- MahaRERA record, where applicable.
- Legal and regulatory compliance.
- Contractual safeguards.
The society should maintain all tender submissions, correspondence, comparative statements and relevant meeting records.
10. Stage Seven: Selection of the Developer
Developer selection is one of the most critical stages of the redevelopment process.
The 2026 Government Order prescribes a Special General Body Meeting for this purpose in the presence of the Registrar’s authorised officer.
The society must follow the prescribed procedure for seeking appointment of the authorised officer and arranging the meeting.
10.1 Documents to Be Submitted
The society is required to submit the relevant redevelopment records, including:
- Managing Committee minutes.
- List of members.
- Project report.
- Tender documents.
- Tenders received.
- Comparative statement.
- Other prescribed records.
The Registrar is required to take the prescribed decision regarding appointment of the authorised officer within the period specified in the Government Order.
10.2 Notice and Quorum
The developer-selection SGM must be convened with at least 14 days’ notice, along with the comparative statement.
The quorum is two-thirds of the total membership.
The Government Order also permits eligible members to participate virtually in the specified circumstances, subject to the physical-presence requirement and other applicable conditions.
10.3 Voting
The developer is selected through the prescribed voting procedure.
The Government Order provides for voting by show of hands, or secret ballot where requested in writing by at least one-fifth of the members.
The selection must receive the approval of at least 51% of the total membership.
Only actual members are entitled to participate as members in the prescribed manner. A representative should not be treated as a substitute for an actual member merely for the purpose of satisfying the voting requirement.
The society must verify the identity of members and maintain proper voting records.
10.4 Video Recording and Submission of Records
The meeting must be video-recorded.
The minutes and prescribed redevelopment records must be submitted to the Registrar within the stipulated period.
The society should preserve the original video recording, attendance records, voting records, minutes and all supporting documents securely.
10.5 Important Distinction: Registrar’s Authorised Officer
The presence of the authorised officer at the developer-selection meeting should not be misunderstood as a general government guarantee of the developer’s financial capability or future performance.
The society remains responsible for carrying out independent due diligence and ensuring that the selected developer is suitable.
11. Stage Eight: Developer Due Diligence
A developer’s commercial offer may appear attractive, but the society must independently verify whether the developer has the financial, technical and legal capacity to complete the project.
The society should not select a developer solely because it offers the highest additional carpet area, corpus or rent.
11.1 Corporate and Financial Verification
The society should examine:
- Legal constitution of the developer.
- Company / LLP / partnership registration.
- Directors, partners and authorised signatories.
- Audited financial statements.
- Net worth and liquidity.
- Existing borrowings and financial obligations.
- Charges and encumbrances.
- Insolvency proceedings, if any.
- Ability to arrange project finance.
11.2 Track Record
The society should verify:
- Completed projects.
- Projects with Occupation Certificates.
- Actual possession records.
- Ongoing projects.
- Construction quality.
- MahaRERA registration and complaint history, where applicable.
- References from earlier societies.
- History of delays and contractual disputes.
11.3 Legal Due Diligence
The society should examine:
- Pending litigation.
- Insolvency or winding-up proceedings.
- Regulatory actions.
- Existing development commitments.
- Joint venture arrangements.
- Third-party rights.
- Mortgage and security arrangements.
- Any restriction on the developer’s ability to perform the proposed project.
11.4 Contractual and Financial Security
The society should obtain appropriate contractual protections, including:
- Adequate bank guarantee.
- Defined validity and renewal requirements.
- Clear conditions for invocation.
- Rent and transit accommodation security.
- Milestone-based obligations.
- Delay compensation.
- Default and termination provisions.
- Appropriate indemnities.
The 2026 Government Order leaves the proportion and form of the bank guarantee to be decided with General Body approval. The earlier 2019 requirement of a fixed 20% bank guarantee should not be represented as a continuing mandatory requirement under the 2026 order.
However, the absence of a fixed percentage does not mean that the society should accept inadequate security.
12. Stage Nine: Execution of the Development Agreement
After the developer has been selected and the necessary due diligence and negotiations are completed, the society must proceed towards execution of the Development Agreement.
The 2026 Government Order requires the agreement to be executed within three months, subject to the terms and conditions approved by the General Body.
The agreement should clearly record the rights, obligations and responsibilities of the society and developer.
12.1 Important Provisions of the Development Agreement
The agreement should adequately address:
A. Property and Development Rights
- Description of the land.
- Existing building details.
- Title and conveyance status.
- Development rights granted.
- Permitted development and applicable approvals.
B. Members’ Entitlements
- Existing area.
- New RERA carpet area.
- Additional area, if agreed.
- Parking entitlement.
- Amenities and common facilities.
- Corpus and other monetary benefits.
C. Transit Accommodation
- Monthly rent.
- Rent escalation.
- Security deposit.
- Brokerage.
- Shifting charges.
- Payment schedule.
- Consequences of delayed payment.
D. Bank Guarantee and Security
- Amount and form.
- Validity.
- Renewal.
- Invocation.
- Release conditions.
E. Construction Obligations
- Specifications.
- Materials.
- Quality standards.
- Project milestones.
- Completion period.
- Approvals and statutory compliance.
F. Default and Termination
- Events of default.
- Notice and cure period.
- Delay consequences.
- Society’s remedies.
- Termination rights.
- Consequences of termination.
G. Third-Party Rights
The agreement should clearly regulate whether and to what extent the developer can assign, transfer, mortgage or otherwise create third-party rights in relation to the development rights.
The 2026 Government Order specifically states that development rights granted to the developer are non-transferable.
12.2 Project Completion Period
The Government Order provides that the redevelopment project should be completed within two years from the date of the commencement / foundation certificate, subject to the specified exceptional circumstances in which the period may extend up to three years.
The agreement should reflect the applicable timeline and provide clear consequences for delay.
12.3 Bank Guarantee
The General Body must decide the proportion and form of the bank guarantee.
The society should consider the overall project cost, construction risk, developer’s financial capacity, possible delay and the cost of protecting members if the project fails.
12.4 Transit Accommodation
The developer is expected to make arrangements for alternative accommodation, monthly rent and deposit, or transit accommodation as contemplated by the Government Order.
The society should ensure that the payment terms and safeguards are sufficiently clear and enforceable.
13. Stage Ten: Individual Permanent Alternate Accommodation Agreements
In addition to the Development Agreement between the society and developer, individual members must enter into Permanent Alternate Accommodation Agreements (PAAA).
The Government Order requires the Development Agreement and individual PAAA to be registered under the Registration Act, 1908.
It further provides that individual PAAA should be executed within three months after registration of the Development Agreement.
13.1 Why Is PAAA Important?
The Development Agreement records the overall redevelopment arrangement between the society and developer.
The PAAA records the individual member’s specific rehabilitation rights.
It should therefore clearly identify:
- Member’s name and existing flat details.
- Existing premises and area.
- New premises entitlement.
- RERA carpet area.
- Floor and flat allocation, where determined.
- Parking entitlement, where applicable.
- Amenities and specifications.
- Rent and transit accommodation.
- Corpus and other benefits.
- Possession timeline.
- Rights and obligations of the parties.
- Consequences of delay or breach.
The PAAA should be consistent with the Development Agreement and should not leave essential member entitlements to informal assurances.
13.2 When Should Members Vacate?
The 2026 Government Order specifically provides that members should vacate their premises only after the required legal approvals are obtained and their individual PAAA have been registered.
This is a significant member-protection measure.
Members should not hand over possession merely on the basis of a developer’s letter, an unregistered draft agreement or an oral promise.
14. Stage Eleven: Statutory Approvals and Commencement of Construction
After execution and registration of the necessary agreements, the developer must obtain the approvals required for the project.
Depending on the property and the applicable regulations, these may include:
- Building plan sanction.
- Commencement Certificate.
- Fire approvals.
- Environmental permissions, where applicable.
- Tree authority permissions, where applicable.
- Airport or other height-related permissions, where applicable.
- Utility and infrastructure permissions.
- MahaRERA registration, where required.
- Other permissions imposed by the competent authority.
The exact list will vary from project to project.
The society should not assume that the execution of a Development Agreement itself authorises demolition or commencement of construction.
The developer must comply with the applicable planning and regulatory requirements.
14.1 RERA Compliance
Where the project or its sale component requires registration under RERA, the developer must comply with the applicable registration and disclosure requirements.
The society should verify the registration details and the obligations undertaken by the developer.
14.2 Approved Plans
The 2026 Government Order contemplates that the plans approved by the Municipal Corporation or competent authority should be placed before the General Body for information.
Members should be given access to the relevant approved documents in accordance with the applicable procedure.
The society should maintain copies of the sanctioned plans, commencement permissions and material revisions.
15. Stage Twelve: Construction, Monitoring and Protection of Members
Once the members have vacated and construction has commenced, the society’s role does not end.
The Managing Committee should monitor the developer’s compliance with the Development Agreement and the approved project documents.
15.1 Construction Monitoring
The society and its professional advisers should periodically review:
- Construction progress.
- Quality of materials.
- Compliance with approved plans.
- Safety arrangements.
- Payment of rent.
- Transit accommodation obligations.
- Bank guarantee validity.
- Insurance.
- Compliance with construction milestones.
- Changes in the project, if any.
15.2 Changes to Approved Plans
Any material change affecting members’ rehabilitation entitlement, building specifications, amenities or common areas should be examined carefully.
The society should ensure that the developer does not make changes contrary to the approved contractual arrangement or applicable legal requirements.
15.3 Delay and Default
The Development Agreement should provide a clear mechanism for dealing with:
- Construction delays.
- Non-payment of rent.
- Failure to renew bank guarantee.
- Material deviation from approved plans.
- Failure to obtain permissions.
- Abandonment of the project.
- Insolvency or financial failure of the developer.
The society should maintain documentary evidence of defaults and obtain timely legal advice before taking contractual action.
16. Stage Thirteen: Completion, Occupation Certificate and Possession
The redevelopment project is not complete merely because the building appears physically ready.
The society should verify that the required statutory approvals and completion documents have been obtained.
16.1 Important Completion Documents
Depending on the project, the society should obtain and verify:
- Occupation Certificate (OC).
- Completion Certificate, where applicable.
- Approved and as-built plans.
- Fire compliance documents.
- Lift and electrical safety documents.
- Water and drainage connection records.
- Equipment warranties.
- Common area and amenity handover records.
- Property and building-related statutory records.
- Defect liability and warranty documents.
16.2 Allotment of Reconstructed Flats
The 2026 Government Order provides for a Special General Body Meeting for allotment of flats in the redeveloped building.
The meeting must be convened with at least 14 days’ notice.
The allocation should, as far as possible, follow the existing floor-wise position. Where allotment by lottery is necessary, the prescribed process should be followed with transparency and video recording.
The minutes, video recording and certified allotment list must be submitted to the Registrar within the period specified in the Government Order.
16.3 Handover and Possession
Before accepting possession, members should verify:
- Actual carpet area.
- Flat number and floor.
- Parking entitlement.
- Fixtures and specifications.
- Water, electricity and other utilities.
- Common areas.
- Amenities.
- Defects and incomplete work.
- Documents and warranties.
The society should also ensure proper handover of common facilities, technical systems, equipment, plans and records.
16.4 New Membership and Share Certificates
The 2026 Government Order requires the society to decide applications for membership from new flat / premises holders within three months after possession and issue membership and share certificates as applicable.
The Managing Committee should ensure that the society’s records are updated and that the new building’s ownership and membership records are properly maintained.
17. Self-Redevelopment and Group Redevelopment
The 2026 Government Order expressly applies to developer-led redevelopment, self-redevelopment and group redevelopment.
17.1 Self-Redevelopment
In self-redevelopment, the society undertakes the project itself, generally engaging professional consultants, contractors and other service providers.
The society may have greater control over the project, but it also assumes substantial financial, technical and execution responsibilities.
The society must carefully examine:
- Project finance.
- Borrowing capacity.
- Contractor selection.
- PMC and architect appointments.
- Construction cost.
- Cost escalation.
- Project management.
- Statutory approvals.
- Insurance and safety.
- Cash flow.
- Risk of contractor default.
Self-redevelopment is not automatically more profitable or less risky than developer-led redevelopment. Its feasibility must be established through a realistic financial and technical assessment.
17.2 Group Redevelopment
The 2026 Government Order also provides for group redevelopment through an eligible cooperative housing federation.
The procedure involves additional requirements relating to the affiliated societies, their approvals and the requisite member support.
Group redevelopment may offer benefits where adjoining societies have a common landholding or a legally connected development arrangement. However, it also creates additional complexities involving title, entitlement, common infrastructure, allocation of development potential and inter-society responsibilities.
These models require separate legal and financial evaluation.
18. Rights of Dissenting, Absent, Deceased and NRI Members
Redevelopment often involves members who do not agree with the proposal, cannot attend meetings, reside abroad or have passed away.
The society should maintain proper membership records and ensure that each member’s rights are dealt with according to the applicable law.
18.1 Dissenting Members
A member’s disagreement with redevelopment does not automatically invalidate a resolution validly passed in accordance with the applicable law and Government Order.
At the same time, majority approval does not authorise the society or developer to disregard statutory requirements, contractual rights or the individual member’s lawful entitlement.
The society should preserve the member’s objections, the meeting record and the legal basis for the decision.
18.2 Absent Members
The society should not treat the mere absence of a member as consent.
The applicable voting and approval requirements must be satisfied through valid participation and voting.
18.3 Deceased Members and Legal Heirs
Where a member has died, the society should verify the membership and succession documentation before dealing with the deceased member’s rights.
Nomination, membership transfer and ultimate ownership are distinct legal questions and should not be treated as interchangeable.
18.4 NRI Members
Members residing outside India may be eligible to participate through virtual means in the circumstances prescribed by the applicable framework.
However, virtual participation in a meeting is distinct from execution and registration of legal documents.
An NRI member may need to comply with separate requirements for execution, attestation, authentication, stamping and registration of documents, depending on the document and the place of execution.
These matters should be addressed well before the society reaches the PAAA stage.
19. Common Mistakes That Can Put a Redevelopment Project at Risk
A society should be alert to the following mistakes:
- Starting the process without examining the society’s legal status and land documents.
- Assuming that the age of the building automatically makes it eligible for redevelopment.
- Ignoring the statutory requirements for convening an SGM.
- Confusing quorum with the required 51% approval.
- Treating absent members’ opinions as votes.
- Appointing a PMC without a clearly defined scope of work.
- Accepting a superficial project report.
- Relying on verbal FSI or carpet-area assurances.
- Preparing tender conditions without proper professional advice.
- Selecting a developer solely on the basis of the highest commercial offer.
- Failing to investigate the developer’s financial capacity and track record.
- Accepting inadequate bank guarantee or transit accommodation security.
- Signing a Development Agreement without clearly defining member entitlements.
- Failing to execute and register individual PAAA.
- Allowing members to vacate before the prescribed approvals and registered agreements are in place.
- Ignoring RERA applicability.
- Failing to monitor construction and rent payments.
- Accepting possession without verifying the Occupation Certificate and other completion documents.
- Failing to preserve meeting minutes, video recordings and statutory correspondence.
- Treating redevelopment as complete without properly handing over the building, common facilities and records.
20. Essential Documents Checklist for Housing Society Redevelopment
The following is a consolidated checklist. The precise documents required will depend on the society, land, project structure and applicable planning authority.
A. Society Documents
- Society Registration Certificate.
- Registered bye-laws and amendments.
- Current membership register.
- Share certificates.
- Managing Committee election records.
- Committee resolutions.
- General Body minutes.
- Audit reports.
- Society financial statements.
B. Land and Title Documents
- Conveyance Deed / Deemed Conveyance documents.
- Original Development Agreement.
- Lease Deed, where applicable.
- Property Card / 7/12 extract.
- City Survey records.
- Land measurement and survey documents.
- Sanctioned layout.
- Approved building plans.
- Occupation Certificate.
- Property tax records.
- Mortgage and encumbrance records.
- Title Search Report.
C. Technical Documents
- Structural Audit Report.
- Structural stability documents, as applicable.
- Architect’s survey.
- Project feasibility report.
- FSI and TDR assessment.
- Site measurements.
- Parking assessment.
- Planning authority correspondence.
- Building specifications.
D. Tender and Developer Documents
- Tender notice.
- Approved tender conditions.
- Tender submissions.
- Comparative statement.
- Developer profile.
- Audited financial statements.
- MahaRERA details, where applicable.
- Project completion records.
- Litigation and insolvency disclosures.
- Bank guarantee proposal.
- Authorisation documents.
E. Contract and Construction Documents
- Development Agreement.
- Individual PAAA.
- Power of Attorney, where required.
- Bank Guarantee.
- Transit rent and accommodation documents.
- Insurance documents.
- Sanctioned building plans.
- Commencement Certificate.
- RERA registration details, where applicable.
- Construction progress records.
- Occupation Certificate.
- Possession letters.
- Defect liability documents.
- As-built drawings.
- Handover records.
21. Frequently Asked Questions About Housing Society Redevelopment
1. Can a housing society undertake redevelopment without the consent of every member?
The 2026 Government Order provides for redevelopment decisions based on the prescribed quorum and approval of at least 51% of the total membership at the relevant stages. Unanimous consent is not the general voting threshold under that procedure. However, the society must comply with all applicable legal requirements and protect individual members’ lawful rights.
2. Can an administrator or Registrar-appointed authorised officer decide to redevelop the society’s building?
The 2026 Government Order states that the redevelopment decision must be taken by a duly elected and legally constituted Managing Committee. It specifically excludes a Registrar-appointed authorised officer, administrator or authorised committee from taking that decision in place of the elected committee.
3. Is a structural audit sufficient to start redevelopment?
Not necessarily. The Government Order refers to a declaration by the competent authority concerning the dangerous or dilapidated condition of the building, along with eligibility under the applicable Development Control Regulations. The legal significance of the structural audit and any competent-authority declaration must be examined separately.
4. Is conveyance of the land compulsory before redevelopment?
The society’s land and conveyance position must be examined as part of the feasibility exercise. The absence of conveyance can create serious legal and practical issues, but it should not be described as an automatic bar in every possible redevelopment structure without examining the title documents and applicable requirements.
5. Can a society appoint a developer before preparing a project report?
The prescribed process requires the selection and appointment of an Architect / PMC and preparation of a project report before the tender and developer-selection stages. A society should not bypass this process by directly appointing a developer on the basis of informal offers.
6. Is the Registrar’s NOC required for redevelopment?
The requirement of a separate Registrar NOC and the requirement of the Registrar’s authorised officer at the developer-selection meeting are distinct issues. The applicable Government directions and current departmental instructions should be examined for the particular procedural step. The society should not assume that the authorised officer’s presence amounts to a general guarantee or approval of the developer’s performance.
7. Is a 20% bank guarantee compulsory under the 2026 Government Order?
The earlier 2019 Government Resolution contained a specific 20% bank guarantee requirement. The 2026 Government Order instead provides that the proportion and form of the bank guarantee should be decided with General Body approval. The society should determine adequate security after considering the project’s risk and financial structure.
8. Can members be asked to vacate before their PAAA is registered?
The 2026 Government Order provides that members should vacate only after the required legal approvals have been obtained and their individual PAAA have been registered. Members should not rely solely on oral assurances or unregistered draft documents.
9. Is MahaRERA registration required for every redevelopment project?
Not necessarily. RERA applicability depends on the project’s structure and the statutory provisions, including the nature of the sale or marketing component and applicable exemptions. The developer and society should obtain a project-specific RERA assessment.
10. What is the prescribed time for completing redevelopment?
The 2026 Government Order provides for completion within two years from the relevant commencement / foundation certificate, with an exceptional extension up to three years in the circumstances contemplated by the order. The Development Agreement should clearly incorporate the applicable timeline and consequences of delay.
11. Can an NRI member participate in redevelopment meetings?
The 2026 Government Order permits virtual participation for specified categories of members and circumstances. The member must comply with the applicable conditions. Execution and registration of the PAAA or other documents may involve separate formalities.
12. Can the society undertake self-redevelopment?
Yes. The 2026 Government Order expressly covers self-redevelopment and applies the prescribed procedure, with necessary adaptation, to the appointment of a contractor. The society must independently assess its financial, technical and legal capacity before choosing this model.
22. Conclusion: Redevelopment Must Be Planned, Documented and Monitored
Housing society redevelopment is a major collective decision with long-term consequences for every member.
The success of a redevelopment project depends not merely on the developer’s offer or the additional carpet area promised. It depends on the society’s legal preparedness, the quality of its project report, the transparency of the tender process, the developer’s financial and technical capacity, and the strength of the Development Agreement and individual PAAA.
Every stage must be supported by proper resolutions, notices, minutes, professional reports, approvals and registered documents.
A society that approaches redevelopment with careful legal and technical planning is better placed to protect its land, its members and its long-term interests.
The guiding principle should be simple: do not proceed on promises when the society’s rights can and should be secured through proper legal documentation.
About Advocate Ketan Palshikar
Advocate Ketan Palshikar practises in Pune, Maharashtra, with a focus on property documentation, conveyancing, title verification and legal due diligence.
For housing societies, property owners and members considering redevelopment, appropriate legal review of title documents, development arrangements, Development Agreements, Permanent Alternate Accommodation Agreements and related property documentation can help identify risks and protect contractual rights.
For professional assistance relating to property documentation and redevelopment agreements, contact Advocate Ketan Palshikar and Associates, Pune.
Related Articles in This 13-Part Redevelopment Guide
- Part 1: Housing Society Redevelopment in Maharashtra: The Complete Step-by-Step Roadmap
- Part 2: 2019 vs 2026 Government Order: What Has Changed in Maharashtra Housing Society Redevelopment?
- Part 3: Before You Begin: Legal, Structural and Financial Checks Before Housing Society Redevelopment
- Part 4: Special General Body Meeting for Redevelopment: Notice, Quorum, Voting and Legal Requirements
- Part 5: Role of Architect and PMC in Housing Society Redevelopment
- Part 6: Tender Process for Housing Society Redevelopment: Rules, Transparency and Developer Offers
- Part 7: Developer Selection in Housing Society Redevelopment: Registrar’s Authorised Officer and Voting Procedure
- Part 8: Developer Due Diligence: How a Housing Society Should Verify a Redeveloper
- Part 9: Development Agreement and PAAA: Protecting Members’ Rights in Redevelopment
- Part 10: From Demolition to Possession: Construction, Approvals and Handover
- Part 11: Self-Redevelopment and Group Redevelopment in Maharashtra
- Part 12: Dissenting, Absent, Deceased and NRI Members in Housing Society Redevelopment
- Part 13: Housing Society Redevelopment FAQs, Legal Checklist and Glossary
- Download Maharashtra Government GR सगृयो-2026/प्र.क्र.108/14-स for Re-Development dated 30/09/2026
Legal Disclaimer
This article is intended for general legal information and educational purposes. It is based on the Government of Maharashtra’s Government Order dated 30 September 2026 and the legal framework referred to above, as understood on the date of publication.
The applicability of redevelopment provisions, development potential, FSI, TDR, planning permissions, RERA requirements, stamp duty and registration formalities may vary depending on the location, land title, society documents, project structure and prevailing law.
A housing society should obtain project-specific legal, technical and financial advice before passing resolutions, selecting a developer, executing agreements or handing over possession.