Introduction

Execution and registration of the Development Agreement mark an important milestone in a housing society redevelopment project. However, the society’s responsibilities do not end there.

The actual implementation phase begins with obtaining the necessary approvals, arranging temporary accommodation, vacating the existing premises, demolition and commencement of construction. The project must then progress through several stages before the developer can hand over the new premises to the existing members.

This is also the stage at which many redevelopment-related problems arise.

Members may face delays in transit rent payments, deviations from approved plans, changes in construction specifications, inadequate construction quality, disputes regarding carpet area, incomplete amenities and delays in obtaining the Occupancy Certificate.

A society that does not monitor the project regularly may discover these issues only when the building is nearing completion, when correcting them can become considerably more difficult.

The Maharashtra Government Order dated 30 September 2026 specifies important requirements concerning the redevelopment timeline, temporary accommodation, registration of individual Permanent Alternate Accommodation Agreements (PAAA), protection of members before they vacate, allotment of premises and submission of approved plans.

This article explains the practical and legal steps that a cooperative housing society should follow from the commencement of construction until the final handover of possession.

1. The Redevelopment Implementation Phase

After execution and registration of the Development Agreement, the project enters its implementation stage.

The major stages ordinarily include:

  1. Obtaining the necessary statutory permissions and sanctions.
  2. Execution and registration of individual PAAA.
  3. Furnishing and verification of the bank guarantee.
  4. Making temporary accommodation arrangements.
  5. Payment of transit rent and agreed deposits.
  6. Vacating the existing premises.
  7. Demolition of the existing building.
  8. Commencement of construction.
  9. Periodic monitoring of construction progress.
  10. Inspection of construction quality and specifications.
  11. Completion of construction and statutory compliance.
  12. Obtaining the Occupancy Certificate, wherever required.
  13. Allotment and identification of permanent alternate premises.
  14. Inspection and rectification of defects.
  15. Handover of possession and relevant documents.

The society should maintain a proper documentary record throughout this process.

The managing committee should not rely exclusively on verbal assurances from the developer. Important communications, approvals, progress reports, inspection records and payment details should be preserved.

2. Legal Approvals Before Members Vacate

One of the most important protections under the 30 September 2026 Government Order concerns the point at which members can be required to vacate their existing premises.

The order provides that members should vacate only after:

  • All necessary legal approvals for redevelopment have been obtained; and
  • The individual Permanent Alternate Accommodation Agreement with the concerned member has been registered.

The rights of persons who are in possession of their existing premises are also required to remain protected.

Accordingly, execution of the Development Agreement alone should not be treated as sufficient authority to require members to vacate.

Documents and arrangements to verify before vacation

The society should verify the following, as applicable to the project:

  • Registered Development Agreement.
  • Necessary permissions and approvals from the competent authority.
  • Sanctioned building plans.
  • Relevant commencement certificate.
  • Registered PAAA of the concerned member.
  • Bank guarantee furnished in accordance with the agreement.
  • Transit accommodation or rent arrangements.
  • Payment of agreed deposit and initial rent, where applicable.
  • Insurance and safety arrangements.
  • Written possession and vacation documentation.

The precise approvals required will depend on the nature of the property, planning authority and project.

Practical safeguard: The Development Agreement should expressly identify the conditions precedent to vacation. Members should not be pressured into handing over possession merely because the developer has announced a proposed demolition date.

3. Execution and Registration of Individual PAAA

The Permanent Alternate Accommodation Agreement is the individual contractual document recording the permanent accommodation entitlement of an existing member.

The 2026 Government Order provides that the PAAA should be registered under the Registration Act, 1908 and executed within three months after registration of the Development Agreement.

The society should monitor whether the developer has completed this process for every eligible member.

What should the PAAA contain?

The PAAA should accurately record:

  • Name and details of the existing member.
  • Existing flat or shop identification.
  • New premises entitlement.
  • RERA carpet area, wherever applicable.
  • Floor and premises identification, if finalised.
  • Parking entitlement, where agreed.
  • Construction specifications.
  • Transit rent and deposit arrangements.
  • Corpus and other financial benefits, where applicable.
  • Project completion and possession obligations.
  • Consequences of delay and other contractual remedies.

The member should verify that the individual PAAA is consistent with the Development Agreement and the member-wise entitlement schedule.

Why is this important?

A member should not have to rely solely on a general resolution or a broad promise contained in the society’s Development Agreement to establish the precise terms of the new premises.

The individual PAAA provides a separate contractual record of the member’s entitlement.

The society should maintain a register recording the date of execution and registration of each PAAA.

4. Transit Rent and Temporary Accommodation: Continuous Monitoring

Temporary accommodation is one of the most immediate concerns for members after they vacate their existing premises.

The 2026 Government Order provides that the developer should arrange alternative accommodation, preferably in the same area, until completion of the project. Alternatively, the developer may arrange monthly rent and deposit acceptable to the members or provide transit camps.

The actual arrangement should be clearly recorded in the Development Agreement and individual PAAA, as applicable.

A. Monthly transit rent

The society should maintain a member-wise rent payment record containing:

  • Name of the member.
  • Existing premises number.
  • Agreed monthly rent.
  • Date from which rent is payable.
  • Due date for each payment.
  • Actual date of payment.
  • Outstanding amount, if any.
  • Agreed escalation, if applicable.

B. Delayed rent payments

If the developer fails to pay rent within the agreed period, the managing committee should issue a written communication identifying the default.

The society should avoid allowing repeated delays to continue without formal documentation.

Depending on the agreement, available contractual remedies may include:

  • Written demand for outstanding rent.
  • Interest on delayed payments.
  • Invocation of agreed security, where permissible.
  • Recovery of unpaid amounts.
  • Other remedies available under the contract and applicable law.

C. Temporary accommodation

Where the developer provides actual accommodation, the society should verify that it is reasonably suitable and that the agreed arrangements remain available until the members are entitled to return to their permanent premises.

D. Rent should not be stopped merely because construction is substantially complete

The agreement should clearly define when the developer’s transit accommodation obligation ends.

The society should not assume that visible completion of the building automatically terminates rent liability. The contractual obligations, required approvals and actual handover conditions must be examined.

5. Bank Guarantee: Validity and Renewal

The bank guarantee is an important financial safeguard against developer default.

The 2026 Government Order provides that the General Body should decide the proportion of the total project cost and the form in which the bank guarantee is to be furnished.

It does not prescribe one universal percentage applicable to every redevelopment project.

Once the amount and terms have been approved and incorporated into the Development Agreement, the society should monitor compliance.

What should the society verify?

  • Whether the bank guarantee has actually been furnished.
  • Whether it is issued by the agreed bank.
  • Whether its authenticity has been independently verified.
  • Whether the amount is correct.
  • Whether it is in favour of the society.
  • Whether its terms are consistent with the Development Agreement.
  • Whether it remains valid.
  • Whether timely renewal or extension is required.
  • Whether the society has received the renewed instrument before expiry of the existing one.

Maintaining a bank guarantee register

The society should maintain a separate record of:

ParticularsDetails to record
Issuing bankName and branch
Guarantee numberReference number
Guarantee amountAmount secured
Date of issueIssue date
Expiry dateValidity end date
Claim periodAs stated in the instrument
Renewal dateDate by which renewal is required
Invocation conditionsContractual conditions

The managing committee should not wait until the expiry date to initiate renewal discussions.

Practical safeguard: The Development Agreement should specify the required validity and renewal mechanism, together with the consequences of failure to renew or replace the guarantee.

6. Project Completion Timeline and Construction Monitoring

The 2026 Government Order provides that the redevelopment project should ordinarily be completed within two years from the date of the first or foundation commencement certificate, as stated in the order.

In exceptional circumstances, the period should not exceed three years.

The society should ensure that the Development Agreement reflects this timeline accurately.

The completion period should not be casually calculated from the date of signing the Development Agreement or from the date members vacate the premises.

A. Construction milestone schedule

The society should obtain a project implementation schedule from the developer and PMC.

A typical monitoring schedule may include:

StageWork to be monitored
Stage 1Statutory approvals and commencement certificate
Stage 2Vacation and handover of existing premises
Stage 3Demolition and site clearance
Stage 4Excavation and foundation
Stage 5Plinth and structural framework
Stage 6Floor-wise construction
Stage 7Masonry and internal partitions
Stage 8Plumbing, electrical and fire systems
Stage 9Plastering, flooring and finishing
Stage 10Elevators and common facilities
Stage 11External development and amenities
Stage 12Completion approvals and possession

The exact sequence and duration will depend on the sanctioned plans and the nature of the project.

B. Periodic progress reports

The society should insist on periodic progress reports from the developer and PMC.

These reports should identify:

  • Work completed during the reporting period.
  • Work currently in progress.
  • Work scheduled for the next period.
  • Delays, if any.
  • Reasons for delay.
  • Pending permissions.
  • Material issues affecting the project.
  • Corrective measures proposed.

C. Site inspections

The society’s PMC or independent technical consultant should periodically inspect the construction site.

The society should not attempt to replace professional engineering supervision with informal visits by committee members.

Technical inspections should be undertaken by qualified professionals.

7. Role of the Architect and PMC During Construction

The Architect or PMC should not be treated as a consultant whose role ends after preparation of the project report.

Where the society has appointed a PMC for the redevelopment project, the scope of engagement should clearly specify the consultant’s responsibilities during construction.

These may include:

  • Reviewing construction progress.
  • Comparing actual work with approved plans.
  • Monitoring construction specifications.
  • Inspecting workmanship and materials.
  • Reviewing developer progress reports.
  • Identifying deviations.
  • Recording deficiencies.
  • Advising the society on corrective measures.
  • Verifying completion of agreed amenities.
  • Assisting with final inspection and handover.

The society should receive periodic written reports rather than relying exclusively on oral updates.

Independent professional oversight

The developer’s architect and engineers are ordinarily engaged by the developer.

The society should therefore ensure that its own appointed Architect or PMC has sufficient independence to report technical issues affecting the society’s interests.

The scope of the consultant’s engagement should be documented, including the frequency of inspections and the format of reports.

8. Monitoring Construction Quality and Specifications

Construction quality is a major factor affecting the long-term safety and usability of the redeveloped building.

The Development Agreement should contain detailed construction specifications. During implementation, the society should verify whether the work conforms to those specifications and approved plans.

Areas requiring monitoring

A. Structural work

  • Foundation.
  • Columns.
  • Beams.
  • Slabs.
  • Reinforcement.
  • Concrete quality.
  • Structural design compliance.

B. Waterproofing

  • Terrace waterproofing.
  • Bathrooms and toilets.
  • Balconies.
  • External walls.
  • Basement and parking areas, where applicable.

C. Electrical systems

  • Internal wiring.
  • Distribution boards.
  • Earthing.
  • Common electrical installations.
  • Emergency lighting.
  • Electrical safety arrangements.

D. Plumbing and drainage

  • Water supply lines.
  • Drainage systems.
  • Rainwater disposal.
  • Overhead and underground tanks.
  • Pumping arrangements.

E. Elevators and fire safety

  • Lift installation and relevant approvals.
  • Fire detection systems.
  • Firefighting equipment.
  • Fire exits and access.
  • Other mandatory fire safety arrangements.

F. Internal finishing

  • Flooring.
  • Doors and windows.
  • Sanitary fittings.
  • Wall finishes.
  • Electrical fixtures.
  • Kitchen and other agreed fittings.

Material substitutions

The developer should not be permitted to substitute specified materials or fittings with inferior alternatives without following the procedure agreed in the Development Agreement.

Where substitution is necessary, the society should obtain the PMC’s technical opinion and ensure that the change is documented.

9. Deviations from Approved Building Plans

Construction must be carried out in accordance with the plans and permissions granted by the competent authority.

The society should be alert to unauthorised deviations, particularly where they affect:

  • Member premises.
  • Carpet area.
  • Building configuration.
  • Common areas.
  • Parking.
  • Open spaces.
  • Access and circulation.
  • Fire safety.
  • Amenities.
  • Structural safety.

The 2026 Government Order requires the approved building plans to be presented before the General Body for information. It also provides that members may apply in writing to the society for copies of approved documents and that the managing committee must supply the information upon payment of the appropriate fee.

What should the society do if a deviation is noticed?

  1. Record the suspected deviation in writing.
  2. Obtain a technical inspection from the society’s PMC or qualified professional.
  3. Compare the actual work with the sanctioned plans.
  4. Seek the developer’s written explanation.
  5. Verify whether the change has been lawfully approved by the competent authority.
  6. Obtain legal advice if the deviation affects member rights or statutory compliance.
  7. Preserve inspection reports, photographs and correspondence.

The society should not accept a verbal assurance that an unauthorised deviation will be regularised later.

10. Changes in Carpet Area or Member Entitlement

The carpet area promised to existing members should be clearly specified in the Development Agreement and individual PAAA.

The 2026 Government Order expressly requires the carpet area payable under the agreement to be mentioned in accordance with RERA.

During construction, the society should monitor whether the premises are being constructed in accordance with the documented entitlement.

Important checks

  • Is the agreed carpet area correctly recorded?
  • Does the construction correspond to the approved plans?
  • Have balconies or other spaces been incorrectly included in the carpet area?
  • Have any changes been made to the member’s premises?
  • Has the developer attempted to reduce the agreed area?
  • Is the final premises identification consistent with the allotment documentation?

If there is a discrepancy, the member should raise it in writing before accepting possession.

The method of measurement and any contractual adjustment should be examined under the PAAA and applicable law.

11. Allotment of Flats in the Redeveloped Building

The 2026 Government Order prescribes a specific procedure for allotment of premises in the redeveloped building.

The society should not allow the developer to allot premises to existing members entirely at its own discretion.

The order provides for a Special General Body Meeting for allotment, with at least 14 days’ notice to all members.

The allotment decision is to be made by a majority of not less than 51% of the society’s total membership present at the meeting.

It further provides that:

  • As far as possible, premises should be allotted floor-wise according to the existing position of members.
  • Where lottery-based allotment is necessary, the developer should arrange the lottery after completion of the building.
  • The society should video-record the allotment meeting.
  • The minutes, video recording and certified allotment list should be submitted to the Registrar’s office within one month.

Recommended documentation

The society should maintain:

  • Notice of the allotment SGM.
  • Proof of service of notice.
  • Attendance record.
  • Relevant General Body resolution.
  • Member-wise allotment statement.
  • Video recording.
  • Certified allotment list.
  • Proof of submission to the Registrar.

The final allotment should be accurately reflected in the individual possession and handover documentation.

12. Completion of Construction and Occupancy Certificate

Physical completion of construction and legal permission to occupy a building are two different matters.

The society should verify that the developer has obtained the Occupancy Certificate or other completion-related approval required from the competent authority before members are asked to occupy the new premises.

The applicable approval and its scope should be examined in the context of the sanctioned plans and the project.

Documents to be examined

Depending on the project and applicable requirements, the society should obtain and verify:

  • Occupancy Certificate.
  • Completion Certificate, where applicable.
  • Approved building plans.
  • Revised sanctioned plans, if any.
  • Relevant commencement certificate.
  • Fire safety compliance documents.
  • Lift approvals and certificates, where applicable.
  • Water and drainage connection records.
  • Other statutory permissions and completion documents.

The society should not treat a developer’s declaration that the building is complete as a substitute for the necessary statutory approval.

Partial Occupancy Certificate

If a partial Occupancy Certificate is issued, the society should examine precisely which building, wing, floor or premises it covers.

The society should not assume that a partial approval automatically permits occupation of every part of the project.

The legal effect of the approval should be checked against the actual building and the competent authority’s conditions.

13. Final Inspection Before Taking Possession

Before accepting possession, the society should arrange a comprehensive inspection with its Architect or PMC.

Members should also be given an opportunity to inspect their individual premises.

A. Inspection of individual premises

Each member should verify:

  • Actual carpet area.
  • Floor and flat number.
  • Doors and windows.
  • Flooring and wall finishes.
  • Electrical fittings.
  • Plumbing and sanitary fittings.
  • Kitchen arrangements, if promised.
  • Balcony and other appurtenant spaces.
  • Fixtures and amenities.
  • General workmanship.

B. Inspection of common areas

The society should inspect:

  • Entrance and lobby.
  • Staircases.
  • Lifts.
  • Parking areas.
  • Terrace.
  • Common toilets, if any.
  • Water tanks and pumps.
  • Electrical rooms.
  • Fire safety systems.
  • Common lighting.
  • Drainage and rainwater systems.
  • Gardens and open spaces.
  • Security systems.
  • Other promised amenities.

C. Defect list

All observed defects and incomplete work should be recorded in a written inspection report.

The report should identify:

  • Location of the defect.
  • Nature of the defect.
  • Photograph, wherever useful.
  • Required corrective work.
  • Person responsible.
  • Time allowed for rectification.

The developer should acknowledge receipt of the defect list and provide a written rectification schedule.

14. Defect Rectification and Construction Liability

The Development Agreement should contain provisions requiring the developer to rectify defects in construction, materials, workmanship and services.

Where RERA applies, the statutory obligations concerning structural defects and other specified defects should also be considered.

Under Section 14(3) of RERA, the promoter is required to rectify specified structural defects and other defects in workmanship, quality or provision of services, or other obligations under the agreement for sale, where reported within the statutory period of five years from handing over possession, without further charge, subject to the statutory conditions.

The precise application of this provision should be examined in the context of the redevelopment project and the concerned premises.

Recommended defect management process

  1. Member or society reports the defect in writing.
  2. The developer acknowledges the complaint.
  3. The defect is inspected by the appropriate technical professional.
  4. Responsibility is determined.
  5. Rectification is carried out within the applicable period.
  6. The society or member verifies the corrective work.
  7. The defect is closed through written confirmation.

The society should preserve defect reports and rectification records even after possession is handed over.

15. Handover of Possession to Existing Members

After obtaining the necessary approvals and completing the agreed contractual requirements, the developer can proceed with handing over possession of the permanent alternate premises.

The society should ensure that possession is properly documented.

Documents for individual members

Each member should receive, as applicable:

  • Registered PAAA.
  • Possession letter.
  • Premises identification details.
  • Carpet area particulars.
  • Parking allotment details, where applicable.
  • Keys and access devices.
  • Relevant approved plan information.
  • Warranty and maintenance information.
  • Other documents agreed under the PAAA.

The member should verify the premises before signing the possession acknowledgement.

The possession letter should not contain an unintended waiver of claims relating to incomplete work, defects or contractual entitlements.

Documents for the society

The society should obtain the documents necessary for the management and maintenance of the redeveloped building, including:

  • Occupancy Certificate and relevant approvals.
  • Approved plans and revisions.
  • Completion-related documents.
  • Structural and technical records, as applicable.
  • Fire safety documents.
  • Lift-related documents.
  • Equipment manuals and warranties.
  • Common facility records.
  • Utility connection details.
  • Insurance information.
  • Relevant contractor and maintenance information.
  • Other records required under the Development Agreement or applicable law.

The society should prepare a formal handover checklist and obtain written acknowledgement of the documents received.

16. Membership and Share Certificates for New Premises Holders

The 2026 Government Order provides that after completion of the redevelopment project or receipt of possession, as stated in the order, the society’s managing committee should decide applications for membership from holders of new flats or commercial premises within three months and issue membership and share certificates.

The society should therefore coordinate with the developer to obtain the information necessary for membership processing.

The records should distinguish between:

  • Existing members receiving permanent alternate accommodation.
  • Persons acquiring premises in the developer’s sale component.
  • Other persons seeking membership under the applicable cooperative law and bye-laws.

Membership applications should be processed in accordance with the applicable provisions of the Maharashtra Co-operative Societies Act, Rules and the society’s registered bye-laws.

The society should not treat every person occupying a premises as automatically admitted as a member without completing the applicable procedure.

17. Maintenance, Common Facilities and Building Records

The society should plan for the transition from construction to regular building management.

The Development Agreement should clearly identify the developer’s responsibility for handing over common facilities and relevant records.

The society should obtain:

  • Details of installed equipment.
  • Operating manuals.
  • Warranty documents.
  • Service contracts, where applicable.
  • Maintenance instructions.
  • Utility details.
  • Common area plans.
  • Fire safety system information.
  • Lift maintenance information.
  • Water supply and drainage information.
  • Other relevant technical records.

The agreement should also deal with any initial maintenance period, maintenance charges and the process for handing over maintenance responsibilities.

The society should ensure that common facilities promised under the agreement are actually completed and functional.

18. What If the Developer Delays Possession?

Delay in handing over possession can cause substantial financial and practical hardship to members.

The society should first examine the Development Agreement and individual PAAA to determine the agreed completion date, permitted extensions and consequences of delay.

The society should maintain a record of:

  • Original project completion timeline.
  • Relevant commencement certificate date.
  • Actual construction progress.
  • Pending statutory approvals.
  • Transit rent payments.
  • Developer’s written explanations.
  • Correspondence concerning delay.
  • Any agreed extension.
  • Outstanding obligations.

Depending on the contractual terms and applicable law, remedies may include:

  • Demand for completion and possession.
  • Continued payment of agreed transit rent.
  • Invocation of bank guarantee, where permissible.
  • Contractual compensation or interest, where provided.
  • Termination in accordance with the agreement and law.
  • Other remedies before the competent forum.

A delay should not automatically be treated as force majeure merely because the developer cites general market conditions or financial difficulties.

The society should obtain legal and technical advice before accepting a revised completion schedule or waiving any contractual right.

19. Final Handover Checklist for the Society

Before treating the redevelopment project as completed and taking over the building, the society should consider the following checklist.

Statutory approvals

  • Occupancy Certificate or applicable completion approval obtained.
  • Approved plans and relevant revisions received.
  • Fire safety compliance documents obtained, where applicable.
  • Lift and other statutory approvals received, where applicable.
  • Utility and other necessary records obtained.

Member entitlements

  • Individual PAAA executed and registered.
  • Member-wise carpet area verified.
  • Allotment procedure completed.
  • Parking and other agreed entitlements documented.
  • Corpus and other benefits paid, where applicable.
  • Transit rent and outstanding dues reconciled.

Construction quality

  • Individual flats inspected.
  • Common areas inspected.
  • Defects recorded.
  • Rectification schedule obtained.
  • Promised amenities verified.
  • Technical documents and warranties received.

Financial and contractual matters

  • Bank guarantee status reviewed.
  • Outstanding contractual payments reconciled.
  • Developer’s obligations under the agreement reviewed.
  • Handover documentation completed.
  • Outstanding claims and reservations documented.

Society records

  • Approved plans and permissions filed.
  • Possession records maintained.
  • Allotment records preserved.
  • Member details updated.
  • New membership applications processed.
  • Share certificates issued in accordance with applicable requirements.
  • Maintenance and technical records received.

20. Common Mistakes During Construction and Handover

1. Assuming that the Development Agreement completes the society’s responsibility

The society must continue to monitor the developer’s performance throughout the project.

2. Allowing members to vacate before the prescribed conditions are satisfied

Necessary approvals and registered individual PAAA should be in place before members are required to vacate.

3. Not monitoring transit rent

Rent defaults should be recorded and addressed promptly.

4. Ignoring bank guarantee expiry

The society should maintain a renewal calendar and verify continued validity.

5. Depending only on the developer’s progress reports

Independent technical monitoring by the society’s PMC or qualified professional is important.

6. Not comparing construction with sanctioned plans

Deviations should be identified and investigated during construction, not after completion.

7. Accepting possession without an Occupancy Certificate where required

Physical completion alone is not a substitute for the necessary statutory approval.

8. Failing to document defects

Every material defect should be recorded in writing with supporting evidence.

9. Signing a blanket satisfaction or waiver

Members and the society should avoid signing documents that unintentionally waive outstanding contractual rights.

10. Not obtaining building records

The society should obtain approved plans, warranties, equipment manuals and other relevant documents before closing the handover process.

21. Frequently Asked Questions

Q1. When can members be asked to vacate their existing flats?

Under the 30 September 2026 Government Order, members should vacate only after all necessary legal approvals have been obtained and their individual PAAA has been registered.

Q2. How long should the redevelopment project take?

The Government Order provides for completion ordinarily within two years from the date of the first or foundation commencement certificate. In exceptional circumstances, the period should not exceed three years.

Q3. Can the developer stop paying transit rent after completing construction?

The answer depends on the contractual arrangement and applicable legal requirements. The society should examine the agreed rent period and the conditions for termination of rent liability. Physical completion alone should not be assumed to end the obligation.

Q4. Is an Occupancy Certificate necessary before members occupy the new building?

The society should verify and obtain the Occupancy Certificate or other legally required approval from the competent authority before permitting occupation, as applicable to the project.

Q5. Can the developer change the sanctioned building plans?

Any proposed change must be examined under the applicable planning regulations and approval requirements. The developer should not be permitted to make unauthorised changes affecting the society’s or members’ contractual rights.

Q6. What should members check before accepting possession?

Members should verify carpet area, premises identification, construction specifications, fittings, amenities, parking entitlement and compliance with the registered PAAA. Any defects or incomplete work should be recorded in writing.

Q7. Can members refuse to accept possession if defects are found?

The member should document the defects and examine the PAAA and applicable law before taking a decision. The existence of a defect does not automatically determine every legal consequence of refusing possession. Appropriate legal and technical advice should be obtained.

Q8. Who is responsible for rectifying construction defects?

The responsibility depends on the Development Agreement, PAAA and applicable law. Where RERA applies, Section 14(3) provides statutory obligations concerning specified defects reported within the prescribed period.

Q9. What documents should the society obtain at final handover?

The society should obtain relevant occupancy and completion approvals, sanctioned plans, technical records, equipment manuals, warranties, fire and lift documents where applicable, utility details and other records required under the agreement.

Q10. Within what period should the society decide new membership applications?

The 2026 Government Order provides for the managing committee to decide applications of new flat or shop holders within three months after completion of the redevelopment project or receipt of possession, as stated in the order, and issue membership and share certificates.

Conclusion

Construction and possession are the stages in which the promises recorded in the Development Agreement and individual PAAA must be translated into actual performance.

The society should maintain active oversight of construction progress, transit rent, bank guarantee validity, compliance with approved plans, construction quality and statutory approvals.

Members should verify their individual entitlements before accepting possession. The society should obtain the necessary completion documents, approved plans, technical records and warranties before treating the handover process as complete.

The 30 September 2026 Government Order provides important protections relating to the project timeline, temporary accommodation, registration of PAAA, protection of members before vacation, flat allotment and access to approved documents.

These requirements should be read together with the Development Agreement, individual PAAA and applicable statutory provisions.

A structured monitoring and handover process helps the society identify problems early, preserve evidence of contractual defaults and protect members’ rights throughout the redevelopment project.


Related Articles in This 13-Part Redevelopment Guide

  1. Part 1: Housing Society Redevelopment in Maharashtra: The Complete Step-by-Step Roadmap
  2. Part 2: 2019 vs 2026 Government Order: What Has Changed in Maharashtra Housing Society Redevelopment?
  3. Part 3: Before You Begin: Legal, Structural and Financial Checks Before Housing Society Redevelopment
  4. Part 4: Special General Body Meeting for Redevelopment: Notice, Quorum, Voting and Legal Requirements
  5. Part 5: Role of Architect and PMC in Housing Society Redevelopment
  6. Part 6: Tender Process for Housing Society Redevelopment: Rules, Transparency and Developer Offers
  7. Part 7: Developer Selection in Housing Society Redevelopment: Registrar’s Authorised Officer and Voting Procedure
  8. Part 8: Developer Due Diligence: How a Housing Society Should Verify a Redeveloper
  9. Part 9: Development Agreement and PAAA: Protecting Members’ Rights in Redevelopment
  10. Part 10: From Demolition to Possession: Construction, Approvals and Handover
  11. Part 11: Self-Redevelopment and Group Redevelopment in Maharashtra
  12. Part 12: Dissenting, Absent, Deceased and NRI Members in Housing Society Redevelopment
  13. Part 13: Housing Society Redevelopment FAQs, Legal Checklist and Glossary
  14. Download Maharashtra Government GR सगृयो-2026/प्र.क्र.108/14-स for Re-Development dated 30/09/2026

Legal Disclaimer: This article is intended for general legal information and educational purposes. The requirements applicable to a particular redevelopment project depend on its title position, sanctioned plans, planning authority, contractual documents and applicable laws. Societies and members should obtain independent legal and technical advice before taking decisions concerning vacation, construction compliance, acceptance of possession or waiver of contractual rights.