Part 6 of 13 · Redevelopment Guide for Housing Societies (Pune & PCMC)
By Advocate Ketan Palshikar | Last updated: 15 November 2026 | Based on Government Order No. SGHYO-2026/CR-108/14-S dated 30 September 2026
1. Introduction
After the society appoints an Architect / Project Management Consultant (PMC) and obtains the Project Report, the next important stage is preparation and invitation of redevelopment tenders.
The tender process is the mechanism through which the society invites eligible and experienced developers to submit their redevelopment proposals in accordance with the society’s approved requirements.
A properly structured tender process serves three important purposes:
- It provides a transparent and competitive opportunity to developers.
- It enables the society to compare proposals on a common basis.
- It helps protect the interests of existing members by establishing clear technical, financial and commercial requirements before a developer is selected.
The tender document is particularly important because it establishes the framework for the proposals that developers will submit. If the tender conditions are vague, incomplete or commercially unrealistic, the society may receive offers that cannot be compared meaningfully.
The Maharashtra Government Order dated 30 September 2026 prescribes a specific procedure for preparation, approval, publication and evaluation of redevelopment tenders.
The relevant provisions are principally contained in Paragraphs 10 and 11 of the Government Order.
2. Legal Framework: Paragraphs 10 and 11 of the 2026 Government Order
The prescribed process can be summarised as follows:
- The Architect / PMC submits the Project Report to the Managing Committee.
- The Managing Committee considers the Project Report and members’ suggestions.
- The Managing Committee discusses and prepares the draft tender document with the assistance of the Architect / PMC.
- Either carpet area or corpus fund must be kept as a fixed, non-variable parameter while formulating the tender.
- The draft tender document is placed before a Special General Body Meeting (SGM) for approval by majority.
- After approval, a public notice inviting tenders must be published in Marathi and English newspapers having the highest local circulation.
- Members may also invite experienced and reputed developers known to them to submit tenders.
- The number of tenders received must be displayed on the society’s notice board after the tender submission deadline.
- A Special General Body Meeting must be convened within 30 days after the last date for receipt of tenders.
- The tenders are opened in the presence of persons attending the meeting.
- The Architect / PMC scrutinises the tenders and prepares a comparative statement.
- If fewer than three tenders are received, the prescribed extensions must be granted before proceeding with the available tenders.
The society should follow this sequence carefully. Tender publication should not be treated as an informal exercise undertaken independently of the approved Project Report and General Body decisions.
3. Preparation of the Redevelopment Tender Document
The first step is preparation of the draft tender document by the Managing Committee with the assistance of the Architect / PMC.
The tender should be based on the Project Report and the redevelopment requirements approved by the society.
It should clearly communicate what the society expects from the developer and the conditions on which the developer is invited to submit an offer.
A tender document should ideally contain the following components.
3.1 Particulars of the Society and Property
The tender should identify:
- Name and registration number of the society.
- Registered address of the society.
- Location and description of the property.
- Survey number, CTS number, Gat number or other applicable land identification.
- Total land area, as per available records.
- Existing building configuration.
- Number of existing residential and commercial premises.
- Existing members and premises details, to the extent relevant.
- Available property and planning documents.
- Details of the applicable planning authority.
The tender should not contain inaccurate land measurements or unverified statements about ownership and development potential.
3.2 Reference to the Project Report
The tender should refer to the Project Report prepared by the Architect / PMC.
Relevant information from the report should be made available to prospective developers so that they can prepare proposals on an informed basis.
The society should identify the development assumptions and technical parameters that are to be followed by all tenderers.
This is important because competing offers should be based on a common understanding of the property and its development potential.
3.3 Existing Members’ Rehabilitation Entitlement
The tender must clearly specify the society’s requirements concerning the rehabilitation of existing members.
These may include:
- Existing carpet area details.
- Proposed additional carpet area, if any.
- Treatment of residential and commercial premises.
- Proposed internal specifications.
- Common facilities and amenities.
- Parking requirements.
- Access and circulation arrangements.
- Other facilities to be provided to existing members.
The society should ensure that the proposed entitlements are realistic and consistent with the applicable planning regulations and the Project Report.
3.4 Corpus Fund
If the society proposes to obtain a corpus fund from the developer, the tender should specify the applicable terms.
These may include:
- Whether corpus is proposed per member or on another approved basis.
- Payment schedule.
- Conditions for payment.
- Whether payment is linked to execution of the Development Agreement, vacation of premises or another milestone.
- Consequences of non-payment.
The society should avoid accepting vague offers such as a lump-sum corpus amount without clearly defining how it will be allocated and paid.
3.5 Temporary Accommodation and Rent
The tender should specify the society’s requirements regarding temporary accommodation during redevelopment.
Depending on the arrangement approved by the society, the tender may address:
- Monthly transit rent.
- Security deposit.
- Brokerage, where agreed.
- Advance rent.
- Annual escalation.
- Payment commencement date.
- Payment frequency.
- Delay-related rent obligations.
- Alternative transit accommodation, where applicable.
The tender should clearly distinguish between the developer’s offer and the minimum requirements prescribed by the society.
3.6 Construction Specifications and Amenities
The tender should contain sufficiently detailed construction specifications.
These may include:
- Structural system.
- Quality and specifications of construction materials.
- Flooring.
- Doors and windows.
- Electrical installations.
- Plumbing and sanitary fittings.
- Lifts.
- Fire-safety systems.
- Water supply arrangements.
- Sewage and drainage systems.
- Internal roads and access.
- Landscaping and garden facilities.
- Common areas.
- Security and other building amenities.
Where possible, the tender should specify measurable technical standards rather than relying on expressions such as “premium quality” or “luxury specifications”.
3.7 Construction and Completion Timeline
The tender should require developers to state their proposed construction schedule and milestones.
The society should also ensure that the tender is consistent with the completion period prescribed by the 2026 Government Order and the applicable contractual and regulatory requirements.
A developer’s proposed timeline should not be accepted merely because it is commercially attractive. Its feasibility should be assessed against approvals, project size, construction methodology, funding and other relevant factors.
3.8 Bank Guarantee and Other Security Requirements
The tender should address the bank guarantee and other security arrangements required for the project.
The 2026 Government Order provides that the General Body is to decide the proportion and form of the bank guarantee.
The society should therefore formulate its requirements through the prescribed process and ensure that the tender does not leave this critical issue undefined.
The tender may also require the developer to provide details of the proposed issuing bank, validity, invocation conditions and renewal obligations, subject to the terms approved by the society.
3.9 Developer Eligibility and Credentials
The society should prescribe appropriate eligibility requirements for prospective developers.
These may include:
- Constitution and registration details of the developer entity.
- Experience in redevelopment projects.
- Details of completed and ongoing projects.
- Technical capacity.
- Financial capacity.
- Litigation and insolvency disclosures, where relevant.
- Details of directors, partners or proprietors.
- Details of professional and technical teams.
- References from previous clients.
- Details of any material defaults in previous projects.
The criteria should be objective, relevant to the project and applied consistently to all tenderers.
4. The Fixed Parameter: Carpet Area or Corpus Fund
One of the important provisions of Paragraph 10 of the 2026 Government Order concerns the manner in which tender conditions are formulated.
The Government Order requires the society to keep either carpet area or corpus fund as a fixed, non-variable parameter while preparing the tender, so that competitive offers can be obtained from experienced and reputed developers.
In practical terms, the society must decide which of these two parameters will remain constant for all tenderers.
Option A: Carpet Area as the Fixed Parameter
Under this approach, the society fixes the carpet area entitlement to be offered to existing members.
All developers must submit their proposals on the basis of the same rehabilitation area.
The competing developers may then be evaluated on other permissible commercial and technical parameters, including corpus, rent, amenities and other benefits, subject to the approved tender conditions.
Illustration:
Suppose the society fixes the additional carpet area entitlement at a specified percentage over the existing eligible carpet area.
Every developer must offer at least that fixed entitlement.
The developers may compete on the remaining permissible parameters, such as corpus fund, transit rent and additional facilities.
Option B: Corpus Fund as the Fixed Parameter
Alternatively, the society may fix the corpus fund requirement.
All developers must offer the same fixed corpus amount or basis, as specified in the tender.
The competing offers may then be evaluated on the basis of other permissible parameters, including additional carpet area and other benefits.
Illustration:
Suppose the society fixes the corpus amount per eligible member.
All developers must offer that same corpus amount.
The competing developers may then be evaluated on the additional carpet area and other permissible benefits offered.
Why Is This Important?
If both carpet area and corpus fund are left entirely variable, developers may submit offers with substantially different combinations of benefits.
One developer may offer more carpet area but a lower corpus, while another may offer less additional area but a higher corpus.
This can make comparison difficult and may result in members focusing on headline figures without considering the overall commercial value.
Keeping one parameter fixed creates a more consistent basis for competition.
The society should carefully consider its members’ priorities and the Project Report before deciding which parameter should remain fixed.
The decision should be reflected clearly in the approved tender document.
5. Approval of the Draft Tender by the Special General Body Meeting
The Managing Committee cannot simply finalise and publish the tender document without following the prescribed approval procedure.
Under Paragraph 10, the draft tender document must be placed before a Special General Body Meeting for approval by majority.
The process should be documented through:
- Notice of the Special General Body Meeting.
- Agenda specifying consideration and approval of the tender draft.
- Copy of the proposed tender document.
- Relevant Project Report and supporting material.
- Attendance and quorum records.
- Minutes recording the discussion and decision.
- Resolution approving the tender document.
Members should have a reasonable opportunity to understand the tender conditions before they are asked to approve them.
Material commercial and technical terms should not be left for informal alteration after approval.
If substantial changes become necessary after approval, the society should obtain appropriate legal and procedural advice on whether the revised tender conditions must again be placed before the General Body.
6. Publication of the Tender Notice
After approval of the tender document by the Special General Body Meeting, the society must invite tenders through the prescribed public notice.
The 2026 Government Order requires publication of the tender invitation in:
- Marathi newspaper; and
- English newspaper,
having the highest local circulation.
The purpose is to provide adequate publicity and attract experienced and reputed developers.
6.1 Contents of the Tender Notice
The notice should ordinarily contain:
- Name of the society.
- Brief description and location of the property.
- Nature of the redevelopment project.
- Reference to the approved tender document.
- Eligibility requirements.
- Place and method for obtaining tender documents.
- Last date and time for submission.
- Contact details for official communication.
- Any other relevant instructions.
The notice should not contain terms that contradict the tender document approved by the General Body.
6.2 Opportunity for Members to Invite Developers
The Government Order also permits society members to inform experienced and reputed developers known to them about the tender and invite them to submit offers.
This provision is significant because the society need not depend exclusively on developers who respond to newspaper advertisements.
Members may help expand the pool of prospective developers, thereby improving competition.
However, every developer must submit its tender in accordance with the same approved tender conditions and within the prescribed deadline.
No member or office bearer should make private commitments or offer preferential treatment to any prospective developer.
7. Receipt and Recording of Tenders
The society should establish a transparent mechanism for receiving tenders.
The process should ensure that all offers are received and recorded properly.
The society should maintain:
- Tender receipt register.
- Date and time of receipt.
- Name and details of the tenderer.
- Acknowledgement of submission.
- Details of any supporting documents received.
- Records of late or incomplete submissions.
- Secure custody of received tenders until the prescribed opening process.
The last date and time for submission should be followed consistently.
The society should not selectively accept late tenders or allow particular developers additional time without a legally valid and uniformly applied basis.
8. Publication of the Number of Tenders Received
Paragraph 11 of the 2026 Government Order specifically requires the Secretary to prepare a list showing the number of tenders received as on the last date for submission.
This list must be published on the society’s notice board.
The purpose is to make the number of responses known to members and maintain transparency at the conclusion of the tender submission stage.
The society should preserve a copy of the displayed list and record the date on which it was published.
9. Special General Body Meeting After Receipt of Tenders
The Secretary must convene a Special General Body Meeting within 30 days after the last date for receipt of tenders.
The Government Order also provides that tenderers or their authorised representatives cannot be prevented from attending the meeting.
This enables the tendering process to be conducted transparently and allows the relevant proposals to be considered in the presence of those attending.
The society should ensure that:
- The meeting is convened within the prescribed period.
- The agenda is properly prepared.
- Members receive the relevant information.
- Tenderers or their authorised representatives are permitted to attend.
- The tenders are opened in the presence of persons attending the meeting.
- The Architect / PMC undertakes the prescribed scrutiny.
- The comparative statement is prepared and presented.
The purpose of this stage is to examine the offers received, not to bypass the subsequent developer-selection procedure.
10. Opening and Scrutiny of Tenders
The 2026 Government Order provides that the received tenders are to be opened in the presence of persons attending the Special General Body Meeting.
The Architect / PMC must scrutinise all tenders and prepare a comparative statement.
The scrutiny should consider the quality, reputation, experience, financial capacity, technical capacity and competitive rates offered by the tenderers.
10.1 Technical Scrutiny
The Architect / PMC should examine whether each tender complies with the technical requirements specified in the approved tender document.
This may include:
- Compliance with the proposed development parameters.
- Proposed carpet area entitlement.
- Construction specifications.
- Amenities and facilities.
- Parking arrangements.
- Project implementation schedule.
- Planning and construction methodology.
- Technical qualifications and supporting documents.
Any material deviation should be specifically identified.
10.2 Financial Scrutiny
The offers should also be examined from a financial perspective.
Relevant considerations may include:
- Corpus fund.
- Transit rent.
- Security deposit.
- Brokerage, if offered.
- Proposed payment schedule.
- Bank guarantee proposal.
- Financial capacity of the developer.
- Funding arrangements.
- Commercial assumptions and qualifications.
The society should not evaluate a financial offer only by looking at the highest headline amount.
The actual terms, conditions, payment security and ability of the developer to fulfil the offer are equally important.
10.3 Experience and Reputation
The Architect / PMC should examine the developer’s experience and reputation.
The evaluation may consider:
- Completed redevelopment projects.
- Ongoing projects.
- Construction quality.
- Project delivery record.
- Financial and technical resources.
- Previous contractual performance.
- Material complaints or defaults, where verifiable.
A developer’s experience in ordinary construction projects should not automatically be treated as equivalent to successful housing society redevelopment experience.
10.4 Comparative Statement
The Architect / PMC must prepare a comparative statement of the tenders.
The statement should present the offers in a structured and consistent manner.
A suggested comparative format is:
| Evaluation parameter | Developer A | Developer B | Developer C |
|---|---|---|---|
| Additional carpet area | As offered | As offered | As offered |
| Corpus fund | As offered | As offered | As offered |
| Monthly transit rent | As offered | As offered | As offered |
| Rent escalation | As offered | As offered | As offered |
| Security deposit | As offered | As offered | As offered |
| Construction specifications | As offered | As offered | As offered |
| Amenities | As offered | As offered | As offered |
| Parking proposal | As offered | As offered | As offered |
| Project timeline | As offered | As offered | As offered |
| Bank guarantee proposal | As offered | As offered | As offered |
| Redevelopment experience | Details | Details | Details |
| Financial capacity | Details | Details | Details |
| Deviations from tender | Details | Details | Details |
The comparative statement should not conceal qualifications, exclusions or deviations.
Where a developer has made a conditional offer, the condition should be clearly disclosed.
11. Minimum Three Tenders: Mandatory Extension Procedure
One of the most important provisions of Paragraph 11 is the requirement concerning the minimum number of tenders.
The Government Order states that at least three tenders are necessary for competitive bidding.
However, it also provides a specific procedure where fewer than three tenders are received.
The prescribed process is:
First Extension: Minimum 15 Days
If fewer than three tenders are received, the society must grant a first extension of at least 15 days.
The objective is to provide additional opportunity for developers to participate.
Second Extension: One Week
If fewer than three tenders are received even after the first extension, the society must grant a second extension of one week.
If Fewer Than Three Tenders Are Still Received
If fewer than three tenders are received even after the second extension, the tenders actually received may be placed before the Special General Body Meeting.
The Government Order therefore does not require the society to abandon the entire process merely because three tenders have not been received after the prescribed extensions.
Illustration:
Suppose the society receives only two tenders by the original deadline.
The society must grant an extension of at least 15 days.
If only two tenders are received after that extension, the society must grant a further extension of one week.
If only two tenders are received even after the second extension, the available tenders may be placed before the Special General Body Meeting.
The society should document the extensions, notices and additional tenders received during each extended period.
12. Revised Tenders by Developers
Paragraph 11 also permits all tenderers who have submitted tenders to submit revised tenders, if they wish to do so.
The Government Order requires the society to follow the prescribed procedure for such revised tenders.
This provision gives participating developers an opportunity to improve their offers.
However, the society should ensure that:
- The opportunity is made available consistently to all relevant tenderers.
- The revised submission procedure is properly recorded.
- The applicable deadline and submission conditions are communicated.
- Revised offers are preserved and evaluated transparently.
- The comparative statement reflects the relevant revised offers.
A revised tender should not become a means of privately negotiating different conditions with individual developers outside the approved process.
13. What the Society Should Not Do During the Tender Process
The following practices should be avoided:
13.1 Changing Tender Conditions Selectively
The society should not allow one developer to benefit from a relaxation or modification that is not made available consistently to other participating developers.
13.2 Accepting Undocumented Offers
Oral offers, informal assurances and private communications should not be treated as substitutes for properly submitted tenders.
13.3 Hiding Material Deviations
The comparative statement should identify important conditions, exclusions and departures from the approved tender document.
13.4 Treating the Highest Offer as Automatically the Best Offer
The financial attractiveness of a proposal must be considered along with technical capacity, financial strength, project experience and the ability to perform contractual obligations.
13.5 Allowing Conflicts of Interest to Influence Evaluation
Any relationship between committee members, office bearers, consultants and prospective developers should be disclosed and dealt with transparently.
13.6 Making the Final Selection at the Tender-Opening Stage
The tender scrutiny and comparative statement are preparatory steps. The final developer-selection process must follow the separate procedure prescribed under Paragraph 12 of the 2026 Government Order.
14. Difference Between Tender Evaluation and Developer Selection
It is important to distinguish between these two stages.
Tender evaluation involves scrutiny of the offers received, verification of compliance, assessment of the developers’ credentials and preparation of a comparative statement by the Architect / PMC.
Developer selection is the subsequent decision-making process conducted through the prescribed Special General Body Meeting in the presence of the Registrar’s authorised officer.
The tender-opening meeting and comparative evaluation should not be confused with the final developer-selection meeting.
The society must follow the separate requirements concerning the Registrar’s authorised officer, notice, quorum, eligible voting members, physical attendance, virtual participation and the prescribed majority for developer selection.
These requirements will be discussed in detail in Part 7 of this series.
15. Practical Checklist for Housing Societies
Before inviting redevelopment tenders, the Managing Committee should verify the following:
- Project Report has been considered and approved through the prescribed process.
- Members’ suggestions have been considered.
- Draft tender document has been prepared with the assistance of the Architect / PMC.
- Carpet area or corpus fund has been fixed as the non-variable parameter.
- Technical and commercial conditions are clearly defined.
- Eligibility criteria for developers have been specified.
- Construction specifications and amenities are sufficiently detailed.
- Transit rent and temporary accommodation requirements are addressed.
- Bank guarantee requirements are incorporated as approved.
- Draft tender has been placed before the Special General Body Meeting.
- Tender document has been approved by majority.
- Public notice has been published in Marathi and English newspapers having the highest local circulation.
- Members have been given the opportunity to invite experienced developers.
- Tenders received have been properly recorded.
- Number of tenders received has been displayed on the notice board.
- Special General Body Meeting has been convened within 30 days after the tender submission deadline.
- Tenderers or their authorised representatives are permitted to attend.
- Tenders are opened in the presence of persons attending the meeting.
- Architect / PMC has scrutinised the tenders.
- Comparative statement has been prepared.
- Minimum three-tender requirement and prescribed extensions have been followed.
- Revised tenders, if any, have been dealt with transparently.
- All notices, minutes, tenders and comparative statements have been preserved.
16. Frequently Asked Questions
Q1. Can the Managing Committee publish the redevelopment tender without approval of the General Body?
The draft tender must be placed before a Special General Body Meeting and approved by majority under Paragraph 10 of the 2026 Government Order. Publication should follow that approval.
Q2. Is it compulsory to obtain at least three tenders?
The Government Order requires at least three tenders for competitive bidding. If fewer than three are received, the prescribed first extension of at least 15 days and second extension of one week must be granted. If fewer than three are still received, the available tenders may be placed before the Special General Body Meeting.
Q3. Can society members recommend developers?
Yes. The Government Order expressly permits members to inform experienced and reputed developers known to them about the tender and invite them to submit offers.
Q4. Must the tender notice be published in both Marathi and English newspapers?
Yes. Paragraph 10 requires a public notice in Marathi and English newspapers having the highest local circulation.
Q5. Within what period must the Special General Body Meeting be called after the last date for tender submission?
The Secretary must convene the meeting within 30 days after the last date for receipt of tenders.
Q6. Can tenderers attend the meeting at which tenders are opened?
Yes. The Government Order states that tenderers or their authorised representatives cannot be prevented from attending the meeting.
Q7. Who scrutinises the tenders and prepares the comparative statement?
The Architect / PMC scrutinises the tenders and prepares the comparative statement.
Q8. Can developers submit revised tenders?
Yes. Paragraph 11 permits all tenderers to submit revised tenders if they wish to do so, subject to the prescribed procedure.
Q9. Can the society select the developer immediately after opening the tenders?
The tender-opening and evaluation process is distinct from the final developer-selection process. Developer selection must follow Paragraph 12, including the prescribed procedure involving the Registrar’s authorised officer.
Q10. Is the developer offering the highest corpus or additional carpet area necessarily the best choice?
No. The society should evaluate the complete offer, including financial capacity, technical competence, redevelopment experience, construction specifications, contractual conditions and the developer’s ability to complete the project.
17. Conclusion
The tender process is one of the most important safeguards in housing society redevelopment.
A properly prepared and approved tender document creates a common framework for all participating developers. Public advertisement, member participation, transparent receipt of tenders, scrutiny by the Architect / PMC and preparation of a comparative statement help the society make an informed decision.
The minimum three-tender requirement and the prescribed extensions are particularly important procedural safeguards under the 2026 Government Order.
The Managing Committee should ensure that every stage is properly documented and that no developer receives an unfair advantage.
The next stage is developer selection through the Special General Body Meeting conducted in the presence of the Registrar’s authorised officer. This stage involves specific requirements concerning notice, quorum, voting, verification of members and approval by the prescribed majority.
Related Articles in This 13-Part Redevelopment Guide
- Part 1: Housing Society Redevelopment in Maharashtra: The Complete Step-by-Step Roadmap
- Part 2: 2019 vs 2026 Government Order: What Has Changed in Maharashtra Housing Society Redevelopment?
- Part 3: Before You Begin: Legal, Structural and Financial Checks Before Housing Society Redevelopment
- Part 4: Special General Body Meeting for Redevelopment: Notice, Quorum, Voting and Legal Requirements
- Part 5: Role of Architect and PMC in Housing Society Redevelopment
- Part 6: Tender Process for Housing Society Redevelopment: Rules, Transparency and Developer Offers
- Part 7: Developer Selection in Housing Society Redevelopment: Registrar’s Authorised Officer and Voting Procedure
- Part 8: Developer Due Diligence: How a Housing Society Should Verify a Redeveloper
- Part 9: Development Agreement and PAAA: Protecting Members’ Rights in Redevelopment
- Part 10: From Demolition to Possession: Construction, Approvals and Handover
- Part 11: Self-Redevelopment and Group Redevelopment in Maharashtra
- Part 12: Dissenting, Absent, Deceased and NRI Members in Housing Society Redevelopment
- Part 13: Housing Society Redevelopment FAQs, Legal Checklist and Glossary
- Download Maharashtra Government GR सगृयो-2026/प्र.क्र.108/14-स for Re-Development dated 30/09/2026
Legal Disclaimer
This article is intended for general legal information and educational purposes. It is based on the Maharashtra Government Order dated 30 September 2026 and should be read with the applicable provisions of the Maharashtra Co-operative Societies Act, 1960, the Maharashtra Co-operative Societies Rules, 1961, applicable development regulations and subsequent amendments or directions. The precise requirements and feasibility of each redevelopment project depend on the society’s property, applicable regulations and the facts of the case. Professional legal and technical advice should be obtained before taking redevelopment decisions.